Permit: T18CM02095
Permit Details
Apply Date:
03/20/2018
Applicant:
N/A
Description:
MECHANIC SHOP
Contractors:
- DURAZO CONSTRUCTION CORPORATION
Permit Reviews
Permit Number - T18CM02095
Permit Status: C of o
Permit Description: MECHANIC SHOP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/20/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 04/04/2018 | COMPLETED |
04/26/2018 | RESUBMITTAL | 05/08/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02095
Permit Status: C of o
Permit Description: MECHANIC SHOP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/20/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM02095
Permit Description: MECHANIC SHOP
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/21/2018 | PLUMBING - ROUGH, SOIL | MRAMBER1 | Approved | IVRS - Inspection :* |
08/30/2018 | BUILDING PRE-SLAB | mramber1 | Approved | |
08/30/2018 | SITE - SEWER | mramber1 | Approved | |
10/10/2018 | SHEET ROCK NAILING | MRAMBER | Approved | |
10/10/2018 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | |
10/19/2018 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | North side restrooms and foyer |
10/19/2018 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | North side restrooms and foyer |
10/19/2018 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | North side restrooms and foyer |
10/19/2018 | BUILDING ABOVE CEILING | ESTEVENS | Approved | North side restrooms and foyer |
10/19/2018 | FRAMING | ESTEVENS | Approved | North side restrooms and foyer |
12/04/2018 | CERTIFICATE OF OCCUPANCY | DMCCARTHY | Approved | |
12/06/2018 | MECHANICAL - FINAL | DMCCARTH | Approved | SOUTHEND WAS ONLY INSPECTED NEED NORTH END DONE |
12/06/2018 | ELECTRIC - FINAL | DMCCARTH | Approved | SOUTHEND WAS ONLY INSPECTED NEED NORTH END DONE |
12/07/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
12/07/2018 | BUILDING - PROGRESS | ESTEVENS | Approved | |
12/07/2018 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
12/07/2018 | PLUMBING - PROGRESS | ESTEVENS | Approved | |
12/13/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
12/13/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
12/13/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
12/14/2018 | ENGINEERING - FINAL | BBENEDON | Approved | |
12/14/2018 | PLUMBING - INTERMEDIATE | DMCCARTHY | Approved | Both bathrooms are complete northside and sell |
12/14/2018 | BUILDING - FINAL | DMCCARTHY | Approved |