Permit: T18CM01872
Permit Details
Apply Date:
03/12/2018
Applicant:
FAHR, GREGORY A
Description:
SFR PLAN2105 T18-M0005 REV 1: SPECIAL INSPECTION FOR POST TENSION SLAB
Architects:
- FAHR, GREGORY A
Contractors:
- CLARKE CUSTOM HOMES INC
Permit Reviews
Permit Number - T18CM01872
Permit Status: Final
Permit Description: SFR PLAN2105 T18-M0005
REV 1: SPECIAL INSPECTION FOR POST TENSION SLAB
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/12/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/12/2018 | COMPLETED |
| 09/20/2018 | REVISION - - 1ST | 09/21/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM01872
Permit Status: Final
Permit Description: SFR PLAN2105 T18-M0005
REV 1: SPECIAL INSPECTION FOR POST TENSION SLAB
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/12/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM01872
Permit Description: SFR PLAN2105 T18-M0005
REV 1: SPECIAL INSPECTION FOR POST TENSION SLAB
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN1 | Approved | |
| 03/14/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | |
| 04/17/2018 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/17/2018 | BUILDING PRE-SLAB | TVALENC1 | Approved | IVRS - Inspection :* |
| 05/30/2018 | ELECTRIC - TEMPORARY SERVICE | DFLORES2 | Approved | CLEAR ECO TEP |
| 05/30/2018 | ROOF NAILING | DFLORES2 | Approved | CLEAR ECO TEP |
| 06/01/2018 | TEP CLEARANCE - AM | DFLORES | Approved | ECO |
| 06/06/2018 | U VALUE FOR WINDOW | DFLORES2 | Approved | |
| 07/02/2018 | MECHANICAL - INTERMEDIATE | B JONES | Approved | |
| 07/02/2018 | PLUMBING - GAS PRESSURE TEST | B JONES | Approved | |
| 07/02/2018 | PLUMBING - INTERMEDIATE | B JONES | Approved | |
| 07/02/2018 | ELECTRIC - INTERMEDIATE | B JONES | Approved | |
| 07/02/2018 | STUCCO MESH | B JONES | Approved | |
| 07/02/2018 | FRAMING | B JONES | Approved | |
| 07/19/2018 | SHEET ROCK NAILING | DFLORES2 | Approved | |
| 09/24/2018 | PLUMBING - FINAL | MHASSAN | Approved | |
| 09/24/2018 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
| 09/24/2018 | ELECTRIC - FINAL | MHASSAN | Approved | |
| 09/24/2018 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN | Approved | |
| 09/24/2018 | ELECTRIC - SERVICE UPGRADE | MHASSAN | Approved | |
| 09/27/2018 | MECHANICAL - FINAL | MHASSAN | Approved | |
| 10/08/2018 | BUILDING - FINAL | KEN | Approved | RECEIVED PT CERT 9/21/2018 |