Permit Details

Status:
Issued
Type:
Commercial Building
Address NEW:
203 E SPEEDWAY BL
Apply Date:
03/07/2018
Applicant:
Lisa Bowers
Description:
TI: STARBUCKS

Permit Reviews

Permit Number - T18CM01765
Permit Status: Issued
Permit Description: TI: STARBUCKS
Start Date Submittal Complete Date Status  
03/07/2018 PLANS OK TO SUBMIT - COMM 03/07/2018 COMPLETED Review Details
03/07/2018 3RD PARTY REVIEW - COMMERCIAL TI 04/16/2018 COMPLETED Review Details
04/16/2018 3RD PARTY REVIEW - COMMERCIAL 07/06/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM01765
Permit Status: Issued
Permit Description: TI: STARBUCKS
Total Outstanding Activity Conditions - 1
Date Name
03/07/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Issued
Permit Number: T18CM01765
Permite Description: TI: STARBUCKS
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
11/04/2022 PDSD Site/Engineering Division - Landscaping N/A Canceled Inspection Canceled
11/04/2022 PDSD Site/Engineering Division - NPPO N/A Canceled Inspection Canceled
11/04/2022 TRSP - ROW - Final/Close-Out N/A Canceled Inspection Canceled
11/04/2022 PDSD Building Division - Sign Final N/A Canceled Inspection Canceled
11/07/2022 COT - LCEL - Electrical Progress N/A Canceled Inspection Canceled
11/07/2022 COT - LCBU - Building Final N/A Canceled Inspection Canceled
11/07/2022 COT - LCPL - Plumbing Progress N/A Canceled Inspection Canceled
11/07/2022 COT - LCEL - Electrical Final N/A Canceled Inspection Canceled
11/07/2022 ENGR Engineering Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Issued
Permit Number: T18CM01765
Permit Description: TI: STARBUCKS
Total Completed Inspections - 19
Date Description Inspector Results Comments
07/11/2018 COT - LCEL - Electrical Underground Passed {Activity date: 07/11/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - }
07/11/2018 COT - LCBU - Preslab Passed {Activity date: 07/11/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - }
07/11/2018 COT - LCPL - Rough Soil Passed {Activity date: 07/11/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - }
07/24/2018 COT - LCBU - Building Above Ceiling Passed {Activity date: 07/24/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - }
07/24/2018 COT - LCBU - Framing Passed {Activity date: 07/24/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - }
07/24/2018 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 07/24/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - REST ROOMS GOOT TO SHEET ROCK, FROM SOPHET TO WEST WALL OK AND ALL OTHER WALLS OK TO ROCK}
07/24/2018 COT - LCPL - Plumbing Intermediate Passed {Activity date: 07/24/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - REST ROOMS GOOT TO SHEET ROCK, FROM SOPHET TO WEST WALL OK AND ALL OTHER WALLS OK TO ROCK}
07/24/2018 COT - LCPL - Plumbing Above Ceiling Passed {Activity date: 07/24/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - REST ROOMS GOOT TO SHEET ROCK, FROM SOPHET TO WEST WALL OK AND ALL OTHER WALLS OK TO ROCK}
07/24/2018 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 07/24/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - }
07/26/2018 COT - BULD - SWG Clearance Passed {Activity date: 07/26/2018; Status: Approved; Inspector: ESTEVENS; Comment: Entered by AMONTIJ2 - }
07/30/2018 COT - LCME - Mechanical Progress Passed {Activity date: 07/30/2018; Status: Approved; Inspector: ESTEVEN1; Comment: Entered by ESTEVEN1 - APPROVED}
07/30/2018 COT - HCBU - Interior Shear Bracing Passed {Activity date: 07/30/2018; Status: Approved; Inspector: ESTEVEN1; Comment: Entered by ESTEVEN1 - APPROVED}
08/23/2018 COT - LCBU - Building Progress Passed {Activity date: 08/23/2018; Status: Approved; Inspector: ESTEVEN1; Comment: Entered by ESTEVEN1 - APPROVED}
10/05/2018 COT - LCEL - Electrical Intermediate Passed {Activity date: 10/05/2018; Status: Approved; Inspector: BJONES; Comment: Entered by BJONES1 - APPROVE BY CONTRACTORS LETTER OF COMPLIANCE WITH THE NEC AND CONSTRUCTION DOCUMENTS} ; {Activity date: 10/04/2018; Status: Partial Approval; Inspector: BJONES; Comment: Entered by CMURPHY1 - APPROVED with a letter from Almonte Electric, THAT STATES THE PROJECT COMPLIES WITH PLANS AND NEC REQUIREMENTS. LETTER ATTACHED TO FILE.
}
10/05/2018 COT - LCPL - Plumbing Final Passed {Activity date: 10/05/2018; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF WATER CHLORINATION REPORT COMPLETED} ; {Activity date: 09/28/2018; Status: Denied; Inspector: ESTEVENS; Comment: Entered by CMURPHY1 - No gas pressure test final, pending water

}
10/09/2018 COT - LCPL - Gas Pressure Test Passed {Activity date: 10/09/2018; Status: Approved; Inspector: MRAMBER; Comment: Entered by CBELL1 - Clarence already approved on a previous inspection}
10/09/2018 COT - LCME - Mechanical Final Passed {Activity date: 10/09/2018; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 09/28/2018; Status: Denied; Inspector: ESTEVENS; Comment: Entered by CMURPHY1 - No intermediate inspection. Pending air balance report}
10/18/2018 COT - FCON - Fire - Final Passed {Activity date: 10/18/2018; Status: Approved; Inspector: jvincent; Comment: Entered by JVINCEN1 - } ; {Activity date: 10/04/2018; Status: Partial Approval; Inspector: jvincent; Comment: Entered by JVINCEN1 - 15" numbers needed on bldg} ; {Activity date: 10/01/2018; Status: Partial Approval; Inspector: jvincent; Comment: Entered by JVINCEN1 - OK TO OBTAIN TCO.
Still needs the following for full final:
1) 15" address numbers.
2) Mount knox box next to riser room.
3) Knox FDC plug.
4) Riser room sign.
5) FACP sign.
6) Mount extinguisher in lobby.
7) Obtain operational permit for "places of assembly"
8) Mount OL sign.
9) Reinspection fee added. Must be paid prior to next inspection.} ; {Activity date: 08/03/2018; Status: Denied; Inspector: jvincent; Comment: Entered by JVINCEN1 - Notes only. Still needs full final. Need to verify they obtained permit for U.G. It was installed w/o permits.}
10/31/2018 COT - LCME - Mechanical Intermediate Passed {Activity date: 10/31/2018; Status: Approved; Inspector: BJONES; Comment: Entered by SVALENZ1 - } ; {Activity date: 10/04/2018; Status: Partial Approval; Inspector: BJONES; Comment: Entered by CMURPHY1 - all that is visible is OK NEED AIR BALANCE REPORT REVIEWED AND APPROVED

}