Permit: T18CM01571
Permit Details
Apply Date:
02/28/2018
Applicant:
EXA ARCHITECTS
Description:
RESTAURANT
Contractors:
- EGGERS CONSTRUCTION , GARY
Permit Reviews
Permit Number - T18CM01571
Permit Status: L of c
Permit Description: RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/28/2018 | COMMERCIAL - TI | 03/06/2018 | COMPLETED |
| 03/06/2018 | RESUBMITTAL | 05/07/2018 | COMPLETED |
| 06/05/2018 | REVISION - - 1ST | 06/06/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM01571
Permit Status: L of c
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/28/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM01571
Permit Description: RESTAURANT
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/08/2018 | ELECTRIC - INTERMEDIATE | bbenedo1 | Approved | |
| 06/13/2018 | FRAMING | JBURGE | Approved | |
| 06/13/2018 | PLUMBING - ABOVE CEILING | JBURGE | Approved | |
| 06/13/2018 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
| 06/13/2018 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | |
| 07/17/2018 | PLUMBING - GAS PRESSURE TEST | ESTEVEN1 | Approved | APPROVED |
| 07/18/2018 | GAS CLEARANCE | ESTEVENS | Approved | |
| 07/20/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | ALL EXISTING PARKING ON AP PLANS TO REMAIN. |
| 07/20/2018 | NPPO - FINAL | RLEDONNE | Approved | |
| 07/20/2018 | SIGN - FINAL | RLEDONNE | Approved | |
| 07/20/2018 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 07/26/2018 | ELECTRIC - SERVICE UPGRADE | B JONES | Approved | |
| 07/26/2018 | ELECTRIC - FINAL | BJONES1 | Approved | IVRS - Inspection :* |
| 08/13/2018 | FIRE - FINAL | CBASALDUA | Approved | |
| 08/14/2018 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | |
| 08/15/2018 | PLUMBING - PRE SLAB | ESTEVEN1 | Approved | |
| 08/15/2018 | SITE - SEWER | ESTEVEN1 | Approved | GREASE TRAP INSPECTED BY BRIAN B. |
| 08/15/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 08/15/2018 | PLUMBING - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/15/2018 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 08/15/2018 | MECHANICAL - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/15/2018 | PLUMBING - GAS PRESS TEST FNL | ESTEVEN1 | Approved | APPROVED |
| 08/15/2018 | ELECTRIC - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/15/2018 | BUILDING - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/15/2018 | RIGHT OF WAY - FINAL | DR | Approved | ROW not impacted. |
| 08/30/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 09/06/2018 | MECHANICAL - HOODS | RSHERRY | Approved | |
| 09/06/2018 | BUILDING - FINAL | RSHERRY | Approved | |
| 09/06/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |