Permit: T18CM01330
Permit Details
Apply Date:
02/21/2018
Applicant:
JOSE L CEJA
Description:
TI: DES REMODEL
Architects:
- JOSE L CEJA
Contractors:
- EPSTEIN CONSTRUCTION L L C
Permit Reviews
Permit Number - T18CM01330
Permit Status: L of c
Permit Description: TI: DES REMODEL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/03/2019 | REVISION - - 1ST | 01/03/2019 | COMPLETED |
02/21/2018 | COMMERCIAL - TI | 01/03/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM01330
Permit Status: L of c
Permit Description: TI: DES REMODEL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/21/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM01330
Permit Description: TI: DES REMODEL
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/27/2018 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
04/27/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
04/27/2018 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED |
08/28/2018 | SHEET ROCK NAILING | JBURGE | Approved | |
11/06/2018 | ELECTRIC - PROGRESS | DMCCARTHY | Approved | |
11/20/2018 | FIRE - FINAL | jvincent | Approved | |
11/20/2018 | FIRE - ALARM FINAL | jvincent | Approved | |
11/20/2018 | FIRE SPKLR - FINAL | jvincent | Approved | |
12/04/2018 | BUILDING - FINAL | DMCCARTHY | Approved | PENDING AIR BALANCE REPORT |
12/04/2018 | ELECTRIC - UFER | DMCCARTHY | Approved | approved upon 2090 approval from Dan M |
12/04/2018 | MECHANICAL - FINAL | DMCCARTHY | Approved | approved upon 4090 approval from Dan M |
12/04/2018 | MECHANICAL - ABOVE CEILING | DMCCARTHY | Approved | approved upon 4090 approval from Dan M |
12/04/2018 | MECHANICAL - INTERMEDIATE | DMCCARTHY | Approved | approved upon 4090 approval from Dan M |
12/04/2018 | BUILDING - PROGRESS | DMCCARTHY | Approved | approved upon 3090 approval from Dan M |
12/04/2018 | PLUMBING - FINAL | DMCCARTHY | Approved | |
12/04/2018 | BUILDING ABOVE CEILING | DMCCARTHY | Approved | approved upon 1090 approval from Dan M |
12/04/2018 | FRAMING | DMCCARTHY | Approved | approved upon 1090 approval from Dan M |
12/04/2018 | ELECTRIC - ABOVE CEILING | DMCCARTHY | Approved | approved upon 2090 approval from Dan M |
12/04/2018 | ELECTRIC - INTERMEDIATE | DMCCARTHY | Approved | approved upon 2090 approval from Dan M |
12/04/2018 | ELECTRIC - FINAL | DMCCARTHY | Approved | |
12/05/2018 | PLUMBING - PROGRESS | DMCCARTHY | Approved | Approved up 3090 approval from Dan M |
02/04/2019 | ENGINEERING - FINAL | BBENEDON | Approved |