Permit: T18CM01180
Permit Details
Apply Date:
02/14/2018
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C
Description:
SFR PEPP0025 T15-M0009
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Permit Reviews
Permit Number - T18CM01180
Permit Status: C of o
Permit Description: SFR PEPP0025 T15-M0009
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 02/16/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM01180
Permit Status: C of o
Permit Description: SFR PEPP0025 T15-M0009
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/14/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM01180
Permit Description: SFR PEPP0025 T15-M0009
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2018 | PLUMBING - SEWER HCS CONNECT | BBENEDO1 | Approved | IVRS - Inspection :* |
| 03/12/2018 | PLUMBING - YARD WTR LINE/TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 03/12/2018 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 03/21/2018 | ELECTRIC - UFER | ESTEVEN1 | Approved | APPROVED |
| 03/21/2018 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
| 03/21/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 04/19/2018 | ROOF NAILING | DFLORES2 | Approved | |
| 04/19/2018 | EXT METAL CLIPS/EXT SHEATHING | DFLORES2 | Approved | |
| 05/23/2018 | STUCCO MESH | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/24/2018 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/24/2018 | PLUMBING - GAS PRESSURE TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/24/2018 | PLUMBING - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/24/2018 | ELECTRIC - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/24/2018 | FRAMING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/06/2018 | SHEET ROCK NAILING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/06/2018 | U VALUE FOR WINDOW | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/29/2018 | ELECTRIC - TEMPORARY SERVICE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/29/2018 | ELECTRIC - CABLE DROP | BBENEDO1 | Approved | IVRS - Inspection :* |
| 07/02/2018 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
| 08/14/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | |
| 08/14/2018 | PLUMBING - FINAL | DFLORES2 | Approved | |
| 08/14/2018 | PLUMBING - GAS PRESS TEST FNL | DFLORES2 | Approved | |
| 08/14/2018 | OUTDOOR LIGHTING FINAL | DFLORES2 | Approved | |
| 08/14/2018 | ELECTRIC - FINAL | DFLORES2 | Approved | |
| 08/14/2018 | BUILDING - PROGRESS | DFLORES2 | Approved | |
| 08/14/2018 | BUILDING - FINAL | DFLORES2 | Approved |