Permit: T18CM01035
Permit Details
Apply Date:
02/09/2018
Applicant:
DELIA MARTINEZ
Description:
TI: OFFICE
Architects:
- JOSE L CEJA
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T18CM01035
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/09/2018 | COMMERCIAL - TI | 02/13/2018 | COMPLETED |
02/13/2018 | RESUBMITTAL - TI ALL | 03/19/2018 | COMPLETED |
03/19/2018 | REVISION - - 1ST | 03/20/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM01035
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/09/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM01035
Permit Description: TI: OFFICE
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/15/2018 | PLUMBING - ROUGH, SOIL | NORTH | Approved | |
03/22/2018 | ELECTRIC - PROGRESS | BJones | Approved | |
03/27/2018 | PLUMBING - PROGRESS | BJones | Approved | |
04/09/2018 | PLUMBING - INTERMEDIATE | BJones | Approved | |
04/09/2018 | ELECTRIC - INTERMEDIATE | BJones | Approved | |
04/12/2018 | ELECTRIC - ABOVE CEILING | BJONES | Approved | Above Ceiling Only In Bathrooms |
04/13/2018 | SHEET ROCK NAILING | BJones | Approved | |
04/13/2018 | FRAMING | BJones | Approved | |
04/16/2018 | PLUMBING - ABOVE CEILING | BJones | Approved | |
04/26/2018 | BUILDING ABOVE CEILING | BJones | Approved | T-Bar Ceiling OK |
04/26/2018 | ELECTRIC - SERVICE UPGRADE | BJones | Approved | |
04/26/2018 | BUILDING ABOVE CEILING | BJones | Approved | |
04/26/2018 | MECHANICAL - ABOVE CEILING | BJones | Approved | |
04/27/2018 | PLUMBING - MEDICAL GAS/FINAL | BJones | Approved | |
04/27/2018 | PLUMBING - MEDICAL GAS/FINAL | BJones | Approved | No Med Gas |
05/01/2018 | TEP CLEARANCE - AM | BJONES | Approved | INCR |
05/30/2018 | FIRE - FINAL | CBASALDUA | Approved | |
05/30/2018 | ENGINEERING - FINAL | DROBERTS | Approved | |
06/01/2018 | CERTIFICATE OF OCCUPANCY | BJONES | Approved | APPROVED PER BUILDING FINAL |
06/01/2018 | MECHANICAL - INTERMEDIATE | BJONES | Approved | APPROVED PER BUILDING FINAL |
06/01/2018 | ELECTRIC - TEMPORARY SERVICE | BJONES | Approved | APPROVED PER BUILDING FINAL |
06/01/2018 | ELECTRIC - CONSTRUCTION POWER | BJONES | Approved | APPROVED PER BUILDING FINAL |
06/01/2018 | PLUMBING - FINAL | RSHERRY | Approved | |
06/01/2018 | MECHANICAL - FINAL | RSHERRY | Approved | |
06/01/2018 | BUILDING - FINAL | RSHERRY | Approved | |
06/01/2018 | PLUMBING - GAS PRESSURE TEST | RSHERRY | Approved | |
06/01/2018 | PLUMBING - MEDICAL GAS/TEST | RSHERRY | Approved | |
06/01/2018 | ELECTRIC - FINAL | RSHERRY | Approved |