Permit: T18CM01025
Permit Details
Apply Date:
02/09/2018
Applicant:
N/A
Description:
NEW 4 PLEX
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- BUILDING EXCELLENCE L L C
- BUILDING EXCELLENCE L L C
Permit Reviews
Permit Number - T18CM01025
Permit Status: C of o
Permit Description: NEW 4 PLEX
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/09/2018 | PLANS OK TO SUBMIT - RES | 02/15/2018 | COMPLETED |
02/15/2018 | RESIDENTIAL - BLDG/WWM | 03/15/2018 | COMPLETED |
03/15/2018 | RESUBMITTAL | 03/16/2018 | COMPLETED |
04/09/2018 | REVISION - - 1ST | 04/19/2018 | COMPLETED |
05/03/2018 | REVISION - - 2ND | 03/18/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM01025
Permit Status: C of o
Permit Description: NEW 4 PLEX
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/09/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM01025
Permit Description: NEW 4 PLEX
Total Completed Inspections - 29
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/05/2018 | ELECTRIC - UFER | DFLORES | Approved | INSPECTIONS WERE CALLED IN ERROR. SHOULD HAVE BEEN FOR BLD 5 |
06/25/2018 | PLUMBING - ROUGH, SOIL | DFLORES2 | Approved | |
07/05/2018 | BUILDING PRE-SLAB | JBURGE | Approved | BUILDING #1: UNITS: #1101, 1102, 1103, 1104; PLUMBING WRAPPED; VAPOR BARRIER IN PLACE. OK TO PLACE CONCRETE. |
08/14/2018 | STUCCO MESH | MHASSAN1 | Approved | BUILDING 4 AND 5 EASTSIDE OK |
08/14/2018 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN1 | Approved | BEARING MIDDLE WALL NEEDS TO BE SHIMMED UNDER MANY TRUSSES. WILL PUT A NOT UNDER FRAMING SO IT WILL GET CHECKED BEFORE SHEETROCK. |
08/14/2018 | ROOF NAILING | MHASSAN1 | Approved | |
09/06/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | IVRS - Inspection :* |
10/09/2018 | FIREWALL/FIREBARRIER/FIRESTOP | BJONES1 | Approved | Bldg 1, Units 1 and 2 previously inspected by E Stevens |
10/19/2018 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
10/19/2018 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | |
10/19/2018 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
10/19/2018 | FRAMING | BSTEVENS | Approved | |
10/31/2018 | SHEET ROCK NAILING | RCAMACHO | Approved | Building 2 south only |
11/26/2018 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Clear electric ECO |
11/27/2018 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
12/11/2018 | TEP CLEARANCE - PM | TVALENCIA | Approved | ECO |
03/01/2019 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | |
03/01/2019 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | |
03/01/2019 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
03/01/2019 | U VALUE FOR WINDOW | JBURGE | Approved | |
03/01/2019 | STEM WALL/RETAINING WALL | JBURGE | Approved | |
03/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | |
03/12/2019 | MECHANICAL - FINAL | ESTEVENS | Approved | |
03/12/2019 | ELECTRIC - FINAL | ESTEVENS | Approved | |
03/12/2019 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
03/12/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
03/18/2019 | FIRE - FINAL | JPeel-Davis | Approved | Added monitoring to backflow preventer. Tested and approved. |
03/18/2019 | BUILDING - FINAL | RSHERRY | Approved | REVIEW OF INSULATION CERTIFICATIONS COMPLETED |
03/18/2019 | PLUMBING - FINAL | ESTEVENS | Approved |