Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM01004
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
15 E PENNINGTON ST
Address NEW:
15 E PENNINGTON ST
Apply Date:
02/08/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: FITNESS CENTER
Architects:
- SAYLER-BROWN, THOMAS
Contractors:
- G 2 CONTRACTING L L C
Permit Reviews
Permit Number - T18CM01004
Permit Status: C of o
Permit Description: TI: FITNESS CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/08/2018 | COMMERCIAL - TI | 02/16/2018 | COMPLETED |
| 02/16/2018 | RESUBMITTAL | 02/20/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM01004
Permit Status: C of o
Permit Description: TI: FITNESS CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/08/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM01004
Permit Description: TI: FITNESS CENTER
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/07/2018 | MECHANICAL - HYDRONIC PIPING | BJones | Approved | |
| 03/07/2018 | ELECTRIC - ABOVE CEILING | BJones | Approved | |
| 03/07/2018 | FRAMING | BJones | Approved | |
| 03/07/2018 | FRAMING | BJones | Approved | |
| 03/13/2018 | PLUMBING - ABOVE CEILING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 03/13/2018 | MECHANICAL - ABOVE CEILING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 03/13/2018 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 03/13/2018 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 03/15/2018 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 03/15/2018 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
| 03/15/2018 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 03/15/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 04/03/2018 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 04/05/2018 | FIRE - FINAL | CBASALDUA | Approved | |
| 04/05/2018 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 04/05/2018 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 04/09/2018 | MECHANICAL - FINAL | mramber1 | Approved | |
| 04/09/2018 | ELECTRIC - FINAL | mramber1 | Approved | |
| 04/09/2018 | PLUMBING - FINAL | mramber1 | Approved | |
| 04/10/2018 | BUILDING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |
| 04/10/2018 | BUILDING - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 04/11/2018 | CERTIFICATE OF OCCUPANCY | MRAMBER | Approved | APPROVED PER BUILDING FINAL - 1090 APPROVAL |