Permit: T18CM00942
Permit Details
Apply Date:
02/06/2018
Applicant:
N/A
Description:
NEW STUDIO
Contractors:
- HOYER KIMURA INC
Permit Reviews
Permit Number - T18CM00942
Permit Status: Final
Permit Description: NEW STUDIO
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/06/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 02/06/2018 | COMPLETED |
| 02/06/2018 | OTHER | 02/20/2018 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T18CM00942
Permit Description: NEW STUDIO
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2018 | PLUMBING - ROUGH, SOIL | rbaldwin | Approved | |
| 02/27/2018 | BUILDING PRE-SLAB | rbaldwin | Approved | |
| 02/27/2018 | EXCAVATION/LAYOUT REBAR & ZON | rbaldwin | Approved | |
| 03/05/2018 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 03/08/2018 | REINFORCED MASONRY PRE-GROUT | rbaldwin | Approved | |
| 03/12/2018 | ROOF NAILING | rbaldwin | Approved | |
| 03/19/2018 | PLUMBING - GAS PRESSURE TEST | rbaldwin | Approved | |
| 03/19/2018 | PLUMBING - INTERMEDIATE | rbaldwin | Approved | |
| 03/19/2018 | ELECTRIC - UNDERGROUND | rbaldwin | Approved | |
| 03/21/2018 | MECHANICAL - INTERMEDIATE | RBALDWIN | Approved | |
| 03/21/2018 | FRAMING | RBALDWIN | Approved | |
| 03/21/2018 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
| 05/01/2018 | MECHANICAL - FINAL | RBALDWIN | Approved | |
| 05/01/2018 | U VALUE FOR WINDOW | RBALDWIN | Approved | |
| 06/12/2018 | OUTDOOR LIGHTING FINAL | mramber1 | Approved | |
| 06/13/2018 | BUILDING - FINAL | mramber1 | Approved | |
| 06/13/2018 | ELECTRIC - FINAL | mramber1 | Approved | |
| 06/13/2018 | PLUMBING - FINAL | mramber1 | Approved |