Permit: T18CM00898
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
6782 E VIA ARROYO LARGO
Address NEW:
6782 E VIA ARROYO LARGO
Apply Date:
02/05/2018
Applicant:
MERITAGE HOMES
Description:
SFR PLAN2740 T16-M0009
Contractors:
- MERITAGE HOMES
- MERITAGE HOMES CONSTRUCTION INC *** APA***
Outstanding Activity Conditions
Permit Number - T18CM00898
Permit Status: Final
Permit Description: SFR PLAN2740 T16-M0009
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/05/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM00898
Permit Description: SFR PLAN2740 T16-M0009
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/07/2018 | PLUMBING - SEWER HCS CONNECT | DFLORES2 | Approved | |
| 03/07/2018 | PLUMBING - YARD WTR LINE/TEST | DFLORES2 | Approved | |
| 03/07/2018 | PLUMBING - ROUGH, SOIL | DFLORES2 | Approved | |
| 03/12/2018 | BUILDING PRE-SLAB | DFLORES2 | Approved | |
| 03/27/2018 | ROOF NAILING | DFLORES2 | Approved | |
| 03/27/2018 | EXT METAL CLIPS/EXT SHEATHING | DFLORES2 | Approved | |
| 04/03/2018 | ELECTRIC - CABLE DROP | MHASSAN1 | Approved | OK TO CLEAR ELECTRIC FOR TEMP POWER |
| 04/04/2018 | TEP CLEARANCE - AM | MHASSAN | Approved | TMPP |
| 04/23/2018 | PLUMBING - GAS PRESSURE TEST | NORTH | Approved | |
| 04/23/2018 | U VALUE FOR WINDOW | NORTH | Approved | |
| 04/23/2018 | STUCCO MESH | NORTH | Approved | |
| 04/26/2018 | MECHANICAL - INTERMEDIATE | MHASSAN1 | Approved | |
| 04/26/2018 | PLUMBING - INTERMEDIATE | MHASSAN1 | Approved | |
| 04/26/2018 | ELECTRIC - INTERMEDIATE | MHASSAN1 | Approved | |
| 04/26/2018 | FRAMING | MHASSAN1 | Approved | |
| 05/09/2018 | SHEET ROCK NAILING | MHASSAN1 | Approved | SHEAR WALL FRONT BEDROOM/BACK WALL UPSTAIRS NEEDS MORE SCREWS AT TOP EDGE. |
| 06/22/2018 | PLUMBING - GAS PRESS TEST FNL | MHASSAN1 | Approved | NEED LONGER FLEX ON WATER HEATER OR PIPE IT SO THERE IS LESS TENSION ON FLEX. |
| 06/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 06/25/2018 | BUILDING - FINAL | DQUINN | Approved | |
| 06/25/2018 | ELECTRIC - UFER | DQUINN | Approved | |
| 06/25/2018 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 06/25/2018 | ELECTRIC - FINAL | DQUINN | Approved | |
| 06/25/2018 | PLUMBING - PRE SLAB | DQUINN | Approved | |
| 06/25/2018 | SITE - SEWER | DQUINN | Approved | |
| 06/25/2018 | PLUMBING - FINAL | DQUINN | Approved | |
| 06/25/2018 | MECHANICAL - FINAL | DQUINN | Approved | |
| 06/26/2018 | GAS CLEARANCE | MHASSAN | Approved |