Permit: T18CM00747
Permit Details
Apply Date:
01/30/2018
Applicant:
ABCO SOLAR
Description:
INSTALL SOLAR PV SYSTEM ON SHADE STRUCTURE
Contractors:
- ABCO SOLAR
Permit Reviews
Permit Number - T18CM00747
Permit Status: Final
Permit Description: INSTALL SOLAR PV SYSTEM ON SHADE STRUCTURE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/30/2018 | PLANS OK TO SUBMIT - COMM | 02/08/2018 | COMPLETED |
| 02/08/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 03/01/2018 | COMPLETED |
| 03/01/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 03/06/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM00747
Permit Status: Final
Permit Description: INSTALL SOLAR PV SYSTEM ON SHADE STRUCTURE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/30/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM00747
Permit Description: INSTALL SOLAR PV SYSTEM ON SHADE STRUCTURE
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/03/2018 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/25/2018 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* CLEASR ELECTRIC DGC |
| 04/25/2018 | ELECTRIC - RECONNECT | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/25/2018 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/25/2018 | BUILDING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/25/2018 | FRAMING | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | TEP CLEARANCE - AM | TVALENCIA | Approved | DGC |