Permit: T18CM00241
Permit Details
Apply Date:
01/10/2018
Applicant:
STOUFFER CONSTRUCTION COMPANY ,
Description:
ADD MASTER SUITE
Contractors:
- STOUFFER CONSTRUCTION COMPANY ,
Permit Reviews
Permit Number - T18CM00241
Permit Status: Final
Permit Description: ADD MASTER SUITE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/10/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 01/10/2018 | COMPLETED |
| 01/10/2018 | RESIDENTIAL - BLDG/WWM | 02/20/2018 | COMPLETED |
| 02/20/2018 | RESUBMITTAL | 02/28/2018 | COMPLETED |
| 02/28/2018 | RESUBMITTAL | 03/02/2018 | COMPLETED |
| 06/14/2018 | REVISION - - 1ST | 06/14/2018 | COMPLETED |
| 08/21/2018 | REVISION - - 2ND | 08/21/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM00241
Permit Status: Final
Permit Description: ADD MASTER SUITE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/10/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM00241
Permit Description: ADD MASTER SUITE
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/27/2018 | PLUMBING - ROUGH, SOIL | NORTH | Approved | |
| 04/03/2018 | BUILDING PRE-SLAB | DFLORES2 | Approved | |
| 04/03/2018 | EXCAVATION/LAYOUT REBAR & ZON | DFLORES2 | Approved | |
| 04/26/2018 | ROOF NAILING | DFLORES2 | Approved | |
| 04/26/2018 | EXT METAL CLIPS/EXT SHEATHING | DFLORES2 | Approved | |
| 05/18/2018 | MECHANICAL - INTERMEDIATE | DFLORES2 | Approved | |
| 05/18/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | |
| 05/18/2018 | ELECTRIC - INTERMEDIATE | DFLORES2 | Approved | |
| 05/18/2018 | FRAMING | DFLORES2 | Approved | |
| 05/30/2018 | U VALUE FOR WINDOW | DFLORES2 | Approved | |
| 05/30/2018 | STUCCO MESH | DFLORES2 | Approved | |
| 08/30/2018 | ELECTRIC - SERVICE UPGRADE | DFLORES2 | Approved | IVRS - Inspection :* |
| 08/31/2018 | TEP CLEARANCE - AM | DFLORES | Approved | INCR |
| 09/28/2018 | PLUMBING - SEWER HCS CONNECT | DFLORES | Approved | Go ahead and close it out thank you |
| 09/28/2018 | MECHANICAL - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |
| 09/28/2018 | PLUMBING - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |
| 09/28/2018 | OUTDOOR LIGHTING FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |
| 09/28/2018 | ELECTRIC - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |
| 09/28/2018 | BUILDING - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |