Permit: T18CM00007
Permit Details
Apply Date:
01/02/2018
Applicant:
PULTE HOME CORP AZ *APA*
Description:
SFR PULT8230-1 T16-M0047
Contractors:
- PULTE DEVELOPMENT CORPORATION ,
Permit Reviews
Permit Number - T18CM00007
Permit Status: Final
Permit Description: SFR PULT8230-1 T16-M0047
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/02/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 01/02/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM00007
Permit Status: Final
Permit Description: SFR PULT8230-1 T16-M0047
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM00007
Permit Description: SFR PULT8230-1 T16-M0047
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/31/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN1 | Approved | |
| 01/31/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN1 | Approved | |
| 01/31/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | |
| 02/05/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | |
| 02/05/2018 | ELECTRIC - UFER | MHASSAN1 | Approved | |
| 02/05/2018 | BUILDING PRE-SLAB | MHASSAN1 | Approved | |
| 02/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN1 | Approved | |
| 03/02/2018 | ROOF NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/02/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/14/2018 | ELECTRIC - CONSTRUCTION POWER | TVALENC1 | Approved | IVRS - Inspection :* CLEAR ELECTRIC ECO |
| 03/14/2018 | ELECTRIC - CABLE DROP | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/15/2018 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
| 03/22/2018 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/22/2018 | PLUMBING - GAS PRESSURE TEST | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/22/2018 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/22/2018 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/22/2018 | U VALUE FOR WINDOW | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/22/2018 | STUCCO MESH | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/22/2018 | FRAMING | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/16/2018 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 05/29/2018 | GAS CLEARANCE | MHASSAN | Approved | |
| 05/29/2018 | PLUMBING - PROGRESS | DFLORES2 | Approved | CLEAR SW GAS |
| 06/11/2018 | MECHANICAL - FINAL | BJONES | Approved | |
| 06/11/2018 | PLUMBING - FINAL | BJONES | Approved | |
| 06/11/2018 | OUTDOOR LIGHTING FINAL | BJONES | Approved | |
| 06/11/2018 | ELECTRIC - FINAL | BJONES | Approved | |
| 06/11/2018 | BUILDING - FINAL | BJONES | Approved |