Permit Details

Status:
Final
Type:
Barricade and Excavation
Apply Date:
11/22/2017
Applicant:
COX COMMUNICATIONS
Description:
Starting on the N/E corner of S. Cherry bell Stravenue and E Silver lake Rd Pull Through Existing Conduit Going S/E for 47' Continue N/E for 404' Placing a 3x3x3 pot hole for Cox Vault, Continue N/E Trench /Bore for 155' Riser up pole and attach new strand and 144 ct fiber going S/E for 748'. on the South Side of E. Fairland Stravenue Riser down pole and Trench/ bore N/W for 100' Placing a 3x3x3 pothole Then continue N/E for 127' to Out of Row 12/13/2017-PLAN CHANGE New:Starting on the N/E corner of S. Cherry bell Stravenue and E Silver lake Rd Pull Through Existing Conduit Going S/E for 47' ,Continue N/E for 404' Placing a 3x3x3 pot hole for Cox Vault, Continue N/E Trench /Bore for 155' Riser up pole and attach new strand and 144 ct fiber going S/E for 3026'', Riser Down Pole and trench/bore 185' Riser up pole and Continue Attaching New Strand and Fiber going S/E for another 2300' on the South Side of E. Fairland Stravenue Riser down pole and Trench/ bore N/W for 100' Placing a 3x3x3 pothole Then continue N/E for 127' to Out of Row

Completed Inspections

Permit Status: Final
Permit Number: T17RW05225
Permit Description: Starting on the N/E corner of S. Cherry bell Stravenue and E Silver lake Rd Pull Through Existing Conduit Going S/E for 47' Continue N/E for 404' Placing a 3x3x3 pot hole for Cox Vault, Continue N/E Trench /Bore for 155' Riser up pole and attach new strand and 144 ct fiber going S/E for 748'. on the South Side of E. Fairland Stravenue Riser down pole and Trench/ bore N/W for 100' Placing a 3x3x3 pothole Then continue N/E for 127' to Out of Row 12/13/2017-PLAN CHANGE New:Starting on the N/E corner of S. Cherry bell Stravenue and E Silver lake Rd Pull Through Existing Conduit Going S/E for 47' ,Continue N/E for 404' Placing a 3x3x3 pot hole for Cox Vault, Continue N/E Trench /Bore for 155' Riser up pole and attach new strand and 144 ct fiber going S/E for 3026'', Riser Down Pole and trench/bore 185' Riser up pole and Continue Attaching New Strand and Fiber going S/E for another 2300' on the South Side of E. Fairland Stravenue Riser down pole and Trench/ bore N/W for 100' Placing a 3x3x3 pothole Then continue N/E for 127' to Out of Row
Total Completed Inspections - 1
Date Description Inspector Results Comments
12/05/2017 TDOT-EXCAV GENERAL INSPECTION cfarren Approved no sign of work being done - CN

Documents

File Name Document Type  
T17RW05225.PDF ROW-RIGHT OF WAY VIEW
T17RW05225 R1.PDF ROW-RIGHT OF WAY VIEW