Description:
RTA Project - spans COT and PC jurisdictions. TEP to Install Approximately 13,562' of 3Ø UG Feeder (1100 kcmil). Complete 2- 6” Feeder Risers. Install 5- PME's, 30-Pulls, Make-Up 17-Pullboxes (Type B). Install Approximately 2,621' of 3Ø UG Primary (1/0 AL 3-2C). Install 1-J2. Install Approximately 145' of 1Ø UG Primary (1/0 AL 2C). Install 1-2.5" Risers Install 6-TEP poles 2-Anchors & 1- OH Transformer. Install Approximately 431 ft. OH Static 4/0 & 477 AAC Primary. Remove Approximately 4,260' of 3Ø UG Feeder (500 kcmil). Remove 3-5” Feeder Risers. Remove 2-PME's,7-Pulls, 14-Pullboxes (Type B). Remove Approximately 11,187' of 3Ø UG Primary (1/0 AL 3-2C). Remove 3-J2's. Remove Approximately 45' of 1Ø UG Primary (1/0 AL 2C). Remove 1-2.5" Risers. Remove 3-TEP poles & 3-Telco Poles & 5-Anchors & 1- OH Transformer. Remove Approximately 431 ft. OH Primary and Static. Work order #'s 6132973, 6173555, and 6132975
Contractors:
  • STURGEON ELECTRIC COMPANY *APA*
  • TRICON CONTRACTING INC *APA*

Completed Inspections

Permit Status: Final
Permit Number: T17RW04597
Permit Description: RTA Project - spans COT and PC jurisdictions. TEP to Install Approximately 13,562' of 3Ø UG Feeder (1100 kcmil). Complete 2- 6” Feeder Risers. Install 5- PME's, 30-Pulls, Make-Up 17-Pullboxes (Type B). Install Approximately 2,621' of 3Ø UG Primary (1/0 AL 3-2C). Install 1-J2. Install Approximately 145' of 1Ø UG Primary (1/0 AL 2C). Install 1-2.5" Risers Install 6-TEP poles 2-Anchors & 1- OH Transformer. Install Approximately 431 ft. OH Static 4/0 & 477 AAC Primary. Remove Approximately 4,260' of 3Ø UG Feeder (500 kcmil). Remove 3-5” Feeder Risers. Remove 2-PME's,7-Pulls, 14-Pullboxes (Type B). Remove Approximately 11,187' of 3Ø UG Primary (1/0 AL 3-2C). Remove 3-J2's. Remove Approximately 45' of 1Ø UG Primary (1/0 AL 2C). Remove 1-2.5" Risers. Remove 3-TEP poles & 3-Telco Poles & 5-Anchors & 1- OH Transformer. Remove Approximately 431 ft. OH Primary and Static. Work order #'s 6132973, 6173555, and 6132975
Total Completed Inspections - 1
Date Description Inspector Results Comments
12/28/2017 TDOT-Routine Barricade Inspect BMONG Approved

Documents

File Name Document Type  
T17RW04597.PDF ROW-RIGHT OF WAY VIEW