Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Barricade and Excavation
Address NEW:
3801 N CAMPBELL AV
Apply Date:
07/05/2017
Applicant:
COX COMMUNICATIONS**B
Description:
Start Point: From TEP Pole on the North side of E Allen Rd and West of N Campbell Ave begin 929' overlash fiber heading East. Riser down 25' place 3x3 asphalt pothole continue 30' underground bore place 1x2 conduit , place 3x3 pothole and a new COX Vault , continue 25' to out of ROW . NOTE: 2000 E Allen Rd was requested - that is not a valid address 7/14/17 - WORK DESCRIPTION CHANGED TO: Start Point: From TEP Pole On the North side of E Allen Rd and West of N Campbell Ave begin 929' overlash fiber heading East . Riser down 25' begin 685' bore/trench heading East . Placing 3x3 potholes 300' to 500' ft. 3x3 asphalt pothole continue 30' underground bore place 1x2 conduit , place 3x3 pothole and a new COX Vault , continue 25' to out of ROW 08/30/2017-PLAN CHANGE/CONTRACTOR/BARRICADE CHANGE Change contractor to CableHawk- Cody Harrington- 520-840-3460- ROC 296924 New Plan: Start Point: From TEP Pole On the North side of E Allen Rd and West of N Campbell Ave begin 290' overlash fiber heading East. Riser down 25' begin 610' bore/trench Placing 3x3 potholes every 300' to 500' heading east, head South. Riser up, begin 670' overlash heading South , from the TEP pole continue 25' overlash to out of ROW Change of Barricade to Southwest Barricades
Contractors:
  • CABLE HAWK COMMUNICATIONS LLC

Completed Inspections

Permit Status: Final
Permit Number: T17RW02898
Permit Description: Start Point: From TEP Pole on the North side of E Allen Rd and West of N Campbell Ave begin 929' overlash fiber heading East. Riser down 25' place 3x3 asphalt pothole continue 30' underground bore place 1x2 conduit , place 3x3 pothole and a new COX Vault , continue 25' to out of ROW . NOTE: 2000 E Allen Rd was requested - that is not a valid address 7/14/17 - WORK DESCRIPTION CHANGED TO: Start Point: From TEP Pole On the North side of E Allen Rd and West of N Campbell Ave begin 929' overlash fiber heading East . Riser down 25' begin 685' bore/trench heading East . Placing 3x3 potholes 300' to 500' ft. 3x3 asphalt pothole continue 30' underground bore place 1x2 conduit , place 3x3 pothole and a new COX Vault , continue 25' to out of ROW 08/30/2017-PLAN CHANGE/CONTRACTOR/BARRICADE CHANGE Change contractor to CableHawk- Cody Harrington- 520-840-3460- ROC 296924 New Plan: Start Point: From TEP Pole On the North side of E Allen Rd and West of N Campbell Ave begin 290' overlash fiber heading East. Riser down 25' begin 610' bore/trench Placing 3x3 potholes every 300' to 500' heading east, head South. Riser up, begin 670' overlash heading South , from the TEP pole continue 25' overlash to out of ROW Change of Barricade to Southwest Barricades
Total Completed Inspections - 1
Date Description Inspector Results Comments
10/12/2017 TDOT-Routine Barricade Inspect DR Approved Final. No Issues.

Documents

File Name Document Type  
T17RW02898.PDF ROW-RIGHT OF WAY VIEW
T17RW02898 R1.PDF ROW-RIGHT OF WAY VIEW
T17RW02898 R2.PDF ROW-RIGHT OF WAY VIEW