Permit: T17CM09417
Permit Details
Apply Date:
12/22/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RESTAURANT
Contractors:
- THORNHILL CONSTRUCTION L L C
Permit Reviews
Permit Number - T17CM09417
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/13/2018 | 3RD PARTY REVIEW - COMMERCIAL | 03/21/2018 | COMPLETED |
12/22/2017 | PLANS OK TO SUBMIT - COMM | 12/22/2017 | COMPLETED |
12/22/2017 | 3RD PARTY REVIEW - COMMERCIAL TI | 03/13/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM09417
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/22/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM09417
Permit Description: RESTAURANT
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/29/2018 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | NOTE: T VALENCIA INSPECTED THE GREASE TRAP ON 2-23-18 AND THE RESULTS WERE PLACE ON THE M W MORRISEY INSPECTION RESULTS. THORNHILL CONSTRUCTION DID NOT HAVE A PERMIT AT THE TIME OF INSPECTION. |
04/04/2018 | ELECTRIC - UNDERGROUND | BJones | Approved | Underground Electrical Conduits for Computer System Futures Only |
04/04/2018 | BUILDING PRE-SLAB | BJones | Approved | |
04/11/2018 | FRAMING | BJones | Approved | |
04/11/2018 | MECHANICAL - INTERMEDIATE | BJones | Approved | |
04/11/2018 | PLUMBING - GAS PRESSURE TEST | BJones | Approved | |
04/11/2018 | PLUMBING - INTERMEDIATE | BJones | Approved | |
04/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENC1 | Approved | IVRS - Inspection :* |
04/17/2018 | SHEET ROCK NAILING | BJones | Approved | |
05/01/2018 | ELECTRIC - PROGRESS | BJones | Approved | Gas and Water Bond Required |
05/01/2018 | ELECTRIC - PROGRESS | BJones | Approved | Gas and Water Bond Required |
05/04/2018 | ELECTRIC - ABOVE CEILING | BBENEDO1 | Approved | IVRS - Inspection :* |
05/04/2018 | PLUMBING - ABOVE CEILING | BBENEDO1 | Approved | IVRS - Inspection :* |
05/04/2018 | GAS CLEARANCE | DQUINN | Approved | |
05/31/2018 | PLUMBING - FINAL | BJONES | Approved | |
05/31/2018 | MECHANICAL - FINAL | BJONES | Approved | |
05/31/2018 | PLUMBING - GAS PRESS TEST FNL | BJONES | Approved | |
05/31/2018 | ELECTRIC - FINAL | BJONES | Approved | |
05/31/2018 | BUILDING - FINAL | BJONES | Approved | 2099,4090,5390,9026,9027,9028,9030,9031,9032 Completed By Others |
05/31/2018 | NPPO - FINAL | RLEDONNE | Approved | |
05/31/2018 | SIGN - FINAL | RLEDONNE | Approved | |
05/31/2018 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
05/31/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | |
06/01/2018 | MECHANICAL - PROGRESS | BJONES | Approved | |
06/01/2018 | MECHANICAL - HOOD SYSTEMS | BJONES | Approved | |
06/01/2018 | MECHANICAL - HOODS | BJONES | Approved | |
06/01/2018 | MECHANICAL - ABOVE CEILING | BJONES | Approved | |
06/01/2018 | PLUMBING - PROGRESS | BJONES | Approved | |
06/01/2018 | OUTDOOR LIGHTING FINAL | BJONES | Approved | |
06/01/2018 | ELECTRIC - OUTDOOR LIGHTING | BJONES | Approved | |
06/01/2018 | ELECTRIC - INTERMEDIATE | BJONES | Approved | |
06/01/2018 | BUILDING - PROGRESS | BJONES | Approved | 2099,4090,5390,9026,9027,9028,9030,9031,9032 Completed By Others |
06/01/2018 | BUILDING ABOVE CEILING | BJONES | Approved | 2099,4090,5390,9026,9027,9028,9030,9031,9032 Completed By Others |
06/01/2018 | RIGHT OF WAY - FINAL | BJONES | Approved | 2099,4090,5390,9026,9027,9028,9030,9031,9032 Completed By Others |
06/01/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
06/01/2018 | FIRE - KITCHEN EXH HOOD FINAL | JPEELDAVIS | Approved | |
06/01/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved |