Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM09408
Permit Details
Apply Date:
12/22/2017
Applicant:
alex enoch
Description:
NEW SFR
Permit Reviews
Permit Number - T17CM09408
Permit Status: Expired
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/29/2018 | RESUBMITTAL | 05/06/2019 | COMPLETED |
05/06/2019 | RESUBMITTAL | 05/21/2019 | COMPLETED |
06/07/2019 | RESUBMITTAL | 06/11/2019 | COMPLETED |
10/08/2019 | REVISION - - 1ST | 10/14/2019 | COMPLETED |
12/22/2017 | PLANS OK TO SUBMIT - RES | 12/26/2017 | COMPLETED |
12/26/2017 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 01/29/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM09408
Permit Status: Expired
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
05/20/2019 | FINAL ELEVATION CERTIFICATE REQUIRED: AN ORIGINAL FINAL ELEVATION CERTIFICATE SEALED BY A REGISTERED LAND SURVEYOR IS REQ'D. MAIL ELEVATION CERTIFICATE TO: CITY OF TUCSON, PLANNING & DEVELOPMENT SERVICES DEPT, ATTN: LOREN MAKUS, P.O. BOX 27210, TUCSON, AZ 85726-7210 OR DELIVER IT TO THE 1ST FL NORTH SIDE OF 201 N. STONE AVE. THIS CONDITION APPLIES TO ALL FINAL INSPECTIONS (1090, 2090, 3090, 4090) AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. |
12/22/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T17CM09408
Permit Status: Expired
Permit Description: NEW SFR
Date | Description | Comments |
---|---|---|
05/20/2019 | SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. | |
05/20/2019 | SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T17CM09408
Permite Description: NEW SFR
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/04/2020 | COT - RSPL - Gas Pressure Test | N/A | Canceled | {Activity date: 09/04/2020; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Not applicable} |
11/07/2022 | ENGR Engineering Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T17CM09408
Permit Description: NEW SFR
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/30/2019 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/30/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/29/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Footing has rain damage at the west side of footprint. Shall clean all cave in areas.} | |
10/29/2019 | COT - RSBU - Stem Wall/Retaining Wall | Passed | {Activity date: 10/29/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/18/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Masonry first lift is okay to grout. } ; {Activity date: 09/25/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Steel reinforcement provided and okay to grout the stem wall. } |
|
10/29/2019 | COT - RSBU - Masonry Pregrout | Passed | {Activity date: 10/29/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - } | |
02/14/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 02/14/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by SFLORES2 - } | |
04/10/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 04/10/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } | |
04/10/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 04/10/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - CODE ECO} | |
04/10/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 04/10/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Clear TEP ECO} | |
08/07/2020 | COT - RSPL - Sewer | Passed | {Activity date: 08/07/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - approved} | |
09/04/2020 | COT - LCBU - Framing | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 02/14/2020; Status: Not ready for Inspection; Inspector: TVALENCIA; Comment: Entered by SFLORES2 - 1- Item called in error} | |
09/04/2020 | COT - RSBU - Preslab | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 03/31/2020; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by SFLORES2 - Steel reinforcement is okay for concrete for the Staircase and demising wall footings.} | |
09/04/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/04/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/04/2020 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/04/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/04/2020 | RSEL - Electrical Progress | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/04/2020 | RSME - Mechanical Progress | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/04/2020 | RSPL - Plumbing Progress | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/04/2020 | COT - RSBU - Sustainability | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
03/17/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 03/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
03/17/2021 | RSBU - Building Final | Passed | {Activity date: 03/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
03/17/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 03/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - } | |
03/17/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 03/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
03/17/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 03/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} |