Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM09271
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
8261 E MAGEE HILL LP
Address NEW:
8261 E MAGEE HILL LP
Apply Date:
12/18/2017
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LENN4067 T16-M0068
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC
Permit Reviews
Permit Number - T17CM09271
Permit Status: Final
Permit Description: SFR LENN4067 T16-M0068
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/18/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 12/18/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM09271
Permit Status: Final
Permit Description: SFR LENN4067 T16-M0068
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/18/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM09271
Permit Description: SFR LENN4067 T16-M0068
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/01/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN1 | Approved | |
| 02/01/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN1 | Approved | |
| 02/01/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | |
| 02/09/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | |
| 02/09/2018 | ELECTRIC - UFER | MHASSAN1 | Approved | |
| 02/09/2018 | BUILDING PRE-SLAB | MHASSAN1 | Approved | |
| 02/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN1 | Approved | |
| 03/11/2018 | ELECTRIC - CONSTRUCTION POWER | MHASSAN1 | Approved | |
| 03/11/2018 | ELECTRIC - CABLE DROP | MHASSAN1 | Approved | |
| 03/12/2018 | ROOF NAILING | NORTH | Approved | |
| 03/12/2018 | EXT METAL CLIPS/EXT SHEATHING | NORTH | Approved | |
| 03/12/2018 | TEP CLEARANCE - AM | MHASSAN | Approved | TMPP |
| 04/17/2018 | MECHANICAL - INTERMEDIATE | DFLORES2 | Approved | |
| 04/17/2018 | PLUMBING - GAS PRESSURE TEST | DFLORES2 | Approved | |
| 04/17/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | |
| 04/17/2018 | ELECTRIC - INTERMEDIATE | DFLORES2 | Approved | |
| 04/17/2018 | U VALUE FOR WINDOW | DFLORES2 | Approved | |
| 04/17/2018 | STUCCO MESH | DFLORES2 | Approved | |
| 04/17/2018 | FRAMING | DFLORES2 | Approved | |
| 04/24/2018 | SHEET ROCK NAILING | DFLORES2 | Approved | |
| 06/18/2018 | PLUMBING - PROGRESS | dflores2 | Approved | CLEAR SW GAS |
| 06/19/2018 | GAS CLEARANCE | DFLORES | Approved | |
| 07/09/2018 | OUTDOOR LIGHTING FINAL | BJONES | Approved | |
| 07/09/2018 | MECHANICAL - FINAL | BJONES1 | Approved | IVRS - Inspection :* |
| 07/09/2018 | PLUMBING - FINAL | BJONES1 | Approved | IVRS - Inspection :* |
| 07/09/2018 | ELECTRIC - FINAL | BJONES1 | Approved | IVRS - Inspection :* |
| 07/09/2018 | BUILDING - FINAL | BJONES1 | Approved | IVRS - Inspection :* |