Permit: T17CM09256
Permit Details
Apply Date:
12/15/2017
Applicant:
O E J ELECTRIC L L C
Description:
INSTALL ROOF MOUNTED SOLAR PV SYSTEM AND METER CONSOLIDATION
Contractors:
- O E J ELECTRIC L L C
Permit Reviews
Permit Number - T17CM09256
Permit Status: Final
Permit Description: INSTALL ROOF MOUNTED SOLAR PV SYSTEM AND METER CONSOLIDATION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/12/2018 | 3RD PARTY REVIEW - COMMERCIAL | 04/30/2018 | COMPLETED |
| 10/08/2018 | REVISION - - 1ST | 10/09/2018 | COMPLETED |
| 12/15/2017 | PLANS OK TO SUBMIT - COMM | 04/12/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM09256
Permit Status: Final
Permit Description: INSTALL ROOF MOUNTED SOLAR PV SYSTEM AND METER CONSOLIDATION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/15/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM09256
Permit Description: INSTALL ROOF MOUNTED SOLAR PV SYSTEM AND METER CONSOLIDATION
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2018 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 05/04/2018 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | |
| 07/26/2018 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 10/18/2018 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | ALL CONNECTIONS IN DISCONNECT, GEAR, AND CT ARE DONE. |
| 10/25/2018 | ELECTRIC - FINAL | MHASSAN | Approved | |
| 10/25/2018 | BUILDING - FINAL | MHASSAN | Approved | |
| 10/26/2018 | TEP CLEARANCE - AM | MHASSAN | Approved | DGC |
| 11/02/2018 | TEP CLEARANCE - PM | MHASSAN | Approved | resent to indicate Meter B |