Permit: T17CM09233
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
485 S STONE AV BLDG#3
Address NEW:
485 S STONE AV BLDG#3
Apply Date:
12/14/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
HOTEL
Architects:
- PAGE REPP
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM09233
Permit Status: C of o
Permit Description: HOTEL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/03/2018 | COMMERCIAL - NEW | 02/27/2018 | COMPLETED |
| 01/10/2019 | REVISION - - 2ND | 04/18/2019 | COMPLETED |
| 03/08/2018 | RESUBMITTAL - TI ALL | 10/25/2018 | COMPLETED |
| 04/18/2019 | REVISION - - 2ND | 04/18/2019 | ACTIVE |
| 04/26/2018 | RESUBMITTAL | 12/05/2018 | COMPLETED |
| 12/11/2018 | REVISION - - 1ST | 12/11/2018 | COMPLETED |
| 12/15/2017 | PLANS OK TO SUBMIT - COMM | 12/19/2017 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM09233
Permit Description: HOTEL
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2018 | ELECTRIC - UFER | MRAMBER | Approved | |
| 10/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | |
| 10/30/2018 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | |
| 11/08/2018 | ELECTRIC - UNDERGROUND | DMCCARTHY | Approved | building number three |
| 11/14/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | building 3, 4 and 5 okay |
| 11/27/2018 | PLUMBING - PRE SLAB | DMCCARTHY | Approved | |
| 11/27/2018 | BUILDING PRE-SLAB | DMCCARTHY | Approved | |
| 01/22/2019 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
| 02/12/2019 | PLUMBING - BACK WATER VALVE | MHASSAN | Approved | |
| 03/04/2019 | ROOF NAILING | MHASSAN | Approved | |
| 03/04/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
| 03/26/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 03/26/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 04/02/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | |
| 09/18/2019 | MECHANICAL - FINAL | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - FINAL | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - FINAL | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - SERVICE UPGRADE | JBURGE | Approved | |
| 09/18/2019 | MECHANICAL - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | |
| 09/18/2019 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | |
| 09/18/2019 | BUILDING - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | SHEET ROCK NAILING | JBURGE | Approved | |
| 09/18/2019 | U VALUE FOR WINDOW | JBURGE | Approved | |
| 09/18/2019 | FRAMING | JBURGE | Approved | |
| 09/24/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 09/24/2019 | RIGHT OF WAY - FINAL | Bravin | Approved | No inspection needed |
| 09/24/2019 | NPPO - FINAL | BBENEDON | Approved | Will inspect these under the development package permit. |
| 09/24/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | Will inspect these under the development package permit. |
| 09/24/2019 | SIGN - FINAL | BBENEDON | Approved | Will inspect these under the development package permit. |
| 10/07/2019 | FIRE - FINAL | MRoss | Approved | |
| 12/05/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 12/23/2019 | BUILDING - FINAL | JCLAXTON | Approved |