Permit: T17CM09173
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
9623 S QUIET DOVE DR
Address NEW:
9623 S QUIET DOVE DR
Apply Date:
12/12/2017
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT721 T16-M0077
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T17CM09173
Permit Status: Final
Permit Description: SFR RICHT721 T16-M0077
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/12/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 12/14/2017 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T17CM09173
Permit Description: SFR RICHT721 T16-M0077
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/26/2017 | PLUMBING - SEWER HCS CONNECT | BBENEDO1 | Approved | IVRS - Inspection :* |
| 12/26/2017 | PLUMBING - YARD WTR LINE/TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 12/26/2017 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 01/04/2018 | ELECTRIC - UNDERGROUND | BBENEDO1 | Approved | IVRS - Inspection :* |
| 01/04/2018 | ELECTRIC - UFER | BBENEDO1 | Approved | IVRS - Inspection :* |
| 01/04/2018 | BUILDING PRE-SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
| 01/17/2018 | ROOF NAILING | RGREENE1 | Approved | |
| 01/17/2018 | EXT METAL CLIPS/EXT SHEATHING | RGREENE1 | Approved | |
| 01/22/2018 | ELECTRIC - CONSTRUCTION POWER | rbaldwin | Approved | |
| 01/22/2018 | ELECTRIC - CABLE DROP | rbaldwin | Approved | |
| 01/30/2018 | MECHANICAL - INTERMEDIATE | DFLORES2 | Approved | |
| 01/30/2018 | PLUMBING - GAS PRESSURE TEST | DFLORES2 | Approved | |
| 01/30/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | |
| 01/30/2018 | ELECTRIC - INTERMEDIATE | DFLORES2 | Approved | |
| 01/30/2018 | U VALUE FOR WINDOW | DFLORES2 | Approved | |
| 01/30/2018 | STUCCO MESH | DFLORES2 | Approved | |
| 01/30/2018 | FRAMING | DFLORES2 | Approved | |
| 01/30/2018 | EXCAVATION/LAYOUT REBAR & ZON | DFLORES2 | Approved | |
| 02/13/2018 | SHEET ROCK NAILING | DFLORES2 | Approved | |
| 03/21/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | CLEAR SW GAS |
| 03/21/2018 | PLUMBING - PROGRESS | DFLORES2 | Approved | CLEAR SW GAS |
| 03/21/2018 | OUTDOOR LIGHTING FINAL | DFLORES2 | Approved | CLEAR SW GAS |
| 03/22/2018 | GAS CLEARANCE | DFLORES | Approved | |
| 04/13/2018 | PLUMBING - FINAL | MHASSAN1 | Approved | |
| 04/17/2018 | ELECTRIC - FINAL | MHASSAN1 | Approved | |
| 04/17/2018 | BUILDING - FINAL | MHASSAN1 | Approved | |
| 07/12/2018 | TEP CLEARANCE - AM | TVALENCIA | Approved | INCR |