Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
12/12/2017
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT721 T16-M0077
Contractors:
  • RICHMOND AMERICAN CONSTRUCTION INC

Permit Reviews

Permit Number - T17CM09173
Permit Status: Final
Permit Description: SFR RICHT721 T16-M0077
Start Date Submittal Complete Date Status  
12/12/2017 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 12/14/2017 COMPLETED Review Details

Completed Inspections

Permit Status: Final
Permit Number: T17CM09173
Permit Description: SFR RICHT721 T16-M0077
Total Completed Inspections - 27
Date Description Inspector Results Comments
12/26/2017 PLUMBING - SEWER HCS CONNECT BBENEDO1 Approved IVRS - Inspection :*
12/26/2017 PLUMBING - YARD WTR LINE/TEST BBENEDO1 Approved IVRS - Inspection :*
12/26/2017 PLUMBING - ROUGH, SOIL BBENEDO1 Approved IVRS - Inspection :*
01/04/2018 ELECTRIC - UNDERGROUND BBENEDO1 Approved IVRS - Inspection :*
01/04/2018 ELECTRIC - UFER BBENEDO1 Approved IVRS - Inspection :*
01/04/2018 BUILDING PRE-SLAB BBENEDO1 Approved IVRS - Inspection :*
01/17/2018 ROOF NAILING RGREENE1 Approved
01/17/2018 EXT METAL CLIPS/EXT SHEATHING RGREENE1 Approved
01/22/2018 ELECTRIC - CONSTRUCTION POWER rbaldwin Approved
01/22/2018 ELECTRIC - CABLE DROP rbaldwin Approved
01/30/2018 MECHANICAL - INTERMEDIATE DFLORES2 Approved
01/30/2018 PLUMBING - GAS PRESSURE TEST DFLORES2 Approved
01/30/2018 PLUMBING - INTERMEDIATE DFLORES2 Approved
01/30/2018 ELECTRIC - INTERMEDIATE DFLORES2 Approved
01/30/2018 U VALUE FOR WINDOW DFLORES2 Approved
01/30/2018 STUCCO MESH DFLORES2 Approved
01/30/2018 FRAMING DFLORES2 Approved
01/30/2018 EXCAVATION/LAYOUT REBAR & ZON DFLORES2 Approved
02/13/2018 SHEET ROCK NAILING DFLORES2 Approved
03/21/2018 MECHANICAL - FINAL DFLORES2 Approved CLEAR SW GAS
03/21/2018 PLUMBING - PROGRESS DFLORES2 Approved CLEAR SW GAS
03/21/2018 OUTDOOR LIGHTING FINAL DFLORES2 Approved CLEAR SW GAS
03/22/2018 GAS CLEARANCE DFLORES Approved
04/13/2018 PLUMBING - FINAL MHASSAN1 Approved
04/17/2018 ELECTRIC - FINAL MHASSAN1 Approved
04/17/2018 BUILDING - FINAL MHASSAN1 Approved
07/12/2018 TEP CLEARANCE - AM TVALENCIA Approved INCR

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW