Permit: T17CM09106
Permit Details
Apply Date:
12/11/2017
Applicant:
TRISTEN HAIGHT
Description:
TI: NEW PHYSICAL THERAPY OFFICE
Contractors:
- TREE STONE CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM09106
Permit Status: C of o
Permit Description: TI: NEW PHYSICAL THERAPY OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/09/2018 | RESUBMITTAL | 01/09/2018 | COMPLETED |
12/11/2017 | COMMERCIAL - TI | 01/09/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM09106
Permit Status: C of o
Permit Description: TI: NEW PHYSICAL THERAPY OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/11/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM09106
Permit Description: TI: NEW PHYSICAL THERAPY OFFICE
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/01/2018 | PLUMBING - ROUGH, SOIL | rbaldwin | Approved | |
03/22/2018 | SHEET ROCK NAILING | DQUINN | Approved | |
03/22/2018 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
03/22/2018 | FRAMING | DQUINN | Approved | |
03/22/2018 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
03/22/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
03/28/2018 | ELECTRIC - CONSTRUCTION POWER | rbaldwin | Approved | |
03/29/2018 | TEP CLEARANCE - AM | RBALDWIN | Approved | ECO |
04/10/2018 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | |
04/10/2018 | MECHANICAL - ABOVE CEILING | mramber1 | Approved | |
04/10/2018 | BUILDING ABOVE CEILING | mramber1 | Approved | |
04/10/2018 | PLUMBING - ABOVE CEILING | mramber1 | Approved | |
04/18/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | |
04/19/2018 | ELECTRIC - SERVICE UPGRADE | mramber1 | Approved | |
04/19/2018 | ELECTRIC - FINAL | mramber1 | Approved | |
04/19/2018 | ELECTRIC - TEMPORARY SERVICE | mramber1 | Approved | |
04/19/2018 | BUILDING - PROGRESS | mramber1 | Approved | |
04/19/2018 | PLUMBING - PROGRESS | mramber1 | Approved | |
05/30/2018 | BUILDING - FINAL | MRAMBER | Approved | |
05/30/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
05/30/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |
06/01/2018 | CERTIFICATE OF OCCUPANCY | mramber | Approved | |
06/01/2018 | FIRE - FINAL | CBASALDUA | Approved | |
06/01/2018 | FIRE SPKLR - FINAL | CBASALDUA | Approved |