Permit: T17CM08925
Permit Details
Apply Date:
12/04/2017
Applicant:
MAYORGA ARMANDO
Description:
NEW SFR
Contractors:
- CIENAGA CANYON CONTRACTORS L L C
Permit Reviews
Permit Number - T17CM08925
Permit Status: Final
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/04/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/04/2017 | COMPLETED |
12/04/2017 | RESIDENTIAL - BLDG/WWM | 12/21/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM08925
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/04/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM08925
Permit Description: NEW SFR
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/08/2018 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED |
01/11/2018 | PLUMBING - SEWER HCS CONNECT | ESTEVEN1 | Approved | APPROVED |
01/11/2018 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
01/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
01/30/2018 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED |
01/30/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED |
02/12/2018 | MECHANICAL - INTERMEDIATE | NORTH | Approved | |
02/12/2018 | PLUMBING - INTERMEDIATE | NORTH | Approved | |
02/12/2018 | ELECTRIC - INTERMEDIATE | NORTH | Approved | |
02/12/2018 | U VALUE FOR WINDOW | NORTH | Approved | |
02/12/2018 | STUCCO MESH | NORTH | Approved | |
02/12/2018 | FRAMING | NORTH | Approved | |
03/05/2018 | ELECTRIC - CONSTRUCTION POWER | MHASSAN1 | Approved | |
03/05/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | |
03/05/2018 | ELECTRIC - UFER | MHASSAN1 | Approved | |
03/06/2018 | TEP CLEARANCE - AM | MHASSAN | Approved | TMPP |
05/29/2018 | PLUMBING - YARD WTR LINE/TEST | DFLORES2 | Approved | |
05/29/2018 | OUTDOOR LIGHTING FINAL | DFLORES2 | Approved | |
05/29/2018 | ELECTRIC - FINAL | DFLORES2 | Approved | |
05/29/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | |
05/29/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | NEED TO CALL IN GAS PRESSURE TEST TO CLEAR SW GAS. NEED INSULATION CERTS,ENERGY CERTS,DOUBLE STAMP CERT |
05/30/2018 | PLUMBING - FINAL | ESTEVEN1 | Approved | APPROVED |
05/30/2018 | PLUMBING - GAS PRESSURE TEST | ESTEVEN1 | Approved | APPROVED |
05/30/2018 | BUILDING - FINAL | ESTEVEN1 | Approved | APPROVED |
05/31/2018 | GAS CLEARANCE | ESTEVENS | Approved |