Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM08625
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
8243 E MAGEE HILL LP
Address NEW:
8243 E MAGEE HILL LP
Apply Date:
11/20/2017
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LENN4075 T16-M0066
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC
Permit Reviews
Permit Number - T17CM08625
Permit Status: Final
Permit Description: SFR LENN4075 T16-M0066
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/20/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 11/29/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM08625
Permit Status: Final
Permit Description: SFR LENN4075 T16-M0066
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/20/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM08625
Permit Description: SFR LENN4075 T16-M0066
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2017 | PLUMBING - SEWER HCS CONNECT | NORTH | Approved | |
| 12/18/2017 | PLUMBING - YARD WTR LINE/TEST | NORTH | Approved | |
| 12/18/2017 | PLUMBING - ROUGH, SOIL | NORTH | Approved | |
| 12/18/2017 | PLUMBING - SEWER HCS CONNECT | aquiroz | Approved | |
| 12/18/2017 | PLUMBING - YARD WTR LINE/TEST | aquiroz | Approved | |
| 12/18/2017 | PLUMBING - ROUGH, SOIL | aquiroz | Approved | |
| 12/21/2017 | ELECTRIC - UFER | NORTH | Approved | REBAR |
| 12/21/2017 | EXCAVATION/LAYOUT REBAR & ZON | NORTH | Approved | |
| 12/21/2017 | BUILDING PRE-SLAB | NORTH | Approved | |
| 01/17/2018 | ROOF NAILING | NORTH | Approved | |
| 01/17/2018 | EXT METAL CLIPS/EXT SHEATHING | NORTH | Approved | |
| 02/02/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | RECN |
| 02/02/2018 | ELECTRIC - CONSTRUCTION POWER | MHASSAN1 | Approved | |
| 02/02/2018 | ELECTRIC - CABLE DROP | MHASSAN1 | Approved | |
| 02/09/2018 | ELECTRIC - INTERMEDIATE | MHASSAN1 | Approved | |
| 02/09/2018 | U VALUE FOR WINDOW | MHASSAN1 | Approved | |
| 02/12/2018 | MECHANICAL - INTERMEDIATE | MHASSAN1 | Approved | |
| 02/12/2018 | PLUMBING - INTERMEDIATE | MHASSAN1 | Approved | FINISH GROUT UNDER TUB |
| 02/12/2018 | FRAMING | MHASSAN1 | Approved | |
| 02/20/2018 | SHEET ROCK NAILING | MHASSAN1 | Approved | |
| 02/20/2018 | STUCCO MESH | MHASSAN1 | Approved | |
| 04/17/2018 | GAS CLEARANCE | DFLORES | Approved | |
| 04/17/2018 | PLUMBING - PROGRESS | DFLORES2 | Approved | CLEAR SW GAS |
| 04/17/2018 | PLUMBING - GAS PRESSURE TEST | DFLORES2 | Approved | CLEAR SW GAS |
| 05/01/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | |
| 05/01/2018 | PLUMBING - FINAL | DFLORES2 | Approved | |
| 05/01/2018 | OUTDOOR LIGHTING FINAL | DFLORES2 | Approved | |
| 05/01/2018 | ELECTRIC - FINAL | DFLORES2 | Approved | |
| 05/01/2018 | BUILDING - FINAL | DFLORES2 | Approved |