Permit: T17CM08493
Permit Details
Apply Date:
11/14/2017
Applicant:
HARRIS, MICHAEL EMERY
Description:
RESIDENTIAL ADDITION
Contractors:
- APOGEE CONSTRUCTION
Outstanding Activity Conditions
Permit Number - T17CM08493
Permit Status: Final
Permit Description: RESIDENTIAL ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/14/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM08493
Permit Description: RESIDENTIAL ADDITION
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/02/2018 | ELECTRIC - SERVICE UPGRADE | ESTEVEN1 | Approved | APPROVED INCR |
| 02/05/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | INCR |
| 02/14/2018 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | OK TO COVER PROGRESS AREA. |
| 04/18/2018 | ROOF NAILING | JBURGE | Approved | |
| 04/18/2018 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
| 07/09/2018 | GAS CLEARANCE | BJONES | Approved | |
| 07/09/2018 | PLUMBING - GAS PRESSURE TEST | BJONES1 | Approved | IVRS - Inspection :* |
| 09/17/2018 | MECHANICAL - INTERMEDIATE | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | PLUMBING - INTERMEDIATE | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | ELECTRIC - INTERMEDIATE | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | U VALUE FOR WINDOW | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | STUCCO MESH | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | FRAMING | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | BUILDING PRE-SLAB | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | DFLORES | Approved | I guess just close em out under my name not much we can do at this point the house is finished and finales, this happens alot I'm starting to notice....I think the customers are taking advantage of our lack of communication...but not much I can do...so we go on I figure ...thank you |
| 09/17/2018 | MECHANICAL - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |
| 09/17/2018 | PLUMBING - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |
| 09/17/2018 | ELECTRIC - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |
| 09/17/2018 | BUILDING - FINAL | DFLORES | Approved | PLEASE FINAL OUT THIS ACTIVITY NUMBER ABOVE THANK YOU |