Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM08139
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3025 N CAMPBELL AV #181
Address NEW:
3025 N CAMPBELL AV #181
Apply Date:
10/31/2017
Applicant:
BRIGHT, RICK LANE
Description:
NAIL SALON TI
Architects:
- BRIGHT, RICK LANE
Contractors:
- C A DEVELOPMENT AND CONSTRUCTION L L C
Permit Reviews
Permit Number - T17CM08139
Permit Status: C of o
Permit Description: NAIL SALON TI
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/31/2017 | COMMERCIAL - TI | 11/03/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM08139
Permit Status: C of o
Permit Description: NAIL SALON TI
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/31/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM08139
Permit Description: NAIL SALON TI
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/16/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED |
| 11/30/2017 | PLUMBING - INTERMEDIATE | JBURGE | Approved | SALON TABLE AREA (16 UNITS) - ROUGH SOIL. OK TO POUR BACK PROGRESS AREA. |
| 12/04/2017 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | SALON TABLES (CONDUITS 1/2" - EIGHT EACH) - BACK FILLED. |
| 01/08/2018 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
| 01/18/2018 | FRAMING | JBURGE | Approved | |
| 01/18/2018 | ELECTRIC - FINAL | JBURGE | Approved | |
| 01/18/2018 | SHEET ROCK NAILING | JBURGE | Approved | OK TO TAPE. |
| 03/01/2018 | MECHANICAL - FINAL | JBURGE | Approved | |
| 03/01/2018 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | |
| 03/01/2018 | PLUMBING - FINAL | JBURGE | Approved | |
| 03/01/2018 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | PENDING ENGINEERING FINAL. |
| 03/01/2018 | BUILDING - FINAL | JBURGE | Approved | PENDING ENGINEERING FINAL. |
| 03/01/2018 | BUILDING ABOVE CEILING | JBURGE | Approved | |
| 03/01/2018 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | |
| 03/01/2018 | FIRE - FINAL | gsereno1 | Approved | |
| 03/02/2018 | ENGINEERING - FINAL | MRUSSO | Approved |