Permit: T17CM08090
Permit Details
Apply Date:
10/27/2017
Applicant:
INLINE CONSTRUCTION INC
Description:
NEW SFR
Contractors:
- INLINE CONSTRUCTION INC
Permit Reviews
Permit Number - T17CM08090
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/27/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 10/27/2017 | COMPLETED |
| 10/27/2017 | RESIDENTIAL - BLDG/WWM | 12/01/2017 | COMPLETED |
| 12/01/2017 | RESUBMITTAL | 12/29/2017 | COMPLETED |
| 12/29/2017 | REVISION - - 1ST | 01/12/2018 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM08090
Permit Description: NEW SFR
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2017 | PLUMBING - ROUGH, SOIL | aquiroz | Approved | |
| 12/19/2017 | ELECTRIC - UFER | RGREENE1 | Approved | |
| 12/19/2017 | BUILDING PRE-SLAB | RGREENE1 | Approved | PIPE PENETRATIONS THROUGH SLAB AND FOOTINGS ARE REQUIRED TO BE WRAPPED. |
| 12/19/2017 | EXCAVATION/LAYOUT REBAR & ZON | RGREENE1 | Approved | |
| 01/04/2018 | FRAMING | NORTH | Approved | |
| 01/04/2018 | ROOF NAILING | NORTH | Approved | |
| 01/05/2018 | EXT METAL CLIPS/EXT SHEATHING | NORTH | Approved | |
| 01/10/2018 | PLUMBING - SEWER HCS CONNECT | rbaldwin | Approved | |
| 01/17/2018 | MECHANICAL - INTERMEDIATE | NORTH | Approved | |
| 01/17/2018 | ELECTRIC - INTERMEDIATE | NORTH | Approved | |
| 01/17/2018 | U VALUE FOR WINDOW | NORTH | Approved | |
| 01/17/2018 | STUCCO MESH | NORTH | Approved | |
| 02/02/2018 | ELECTRIC - CONSTRUCTION POWER | NORTH | Approved | |
| 02/02/2018 | ELECTRIC - CABLE DROP | NORTH | Approved | |
| 02/05/2018 | TEP CLEARANCE - AM | NORTH | Approved | INCR |
| 03/08/2018 | MECHANICAL - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/08/2018 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/08/2018 | OUTDOOR LIGHTING FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/13/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN1 | Approved | WAY BEYOND THIS AT THE TIME OF MY INSPECTION |
| 03/13/2018 | PLUMBING - INTERMEDIATE | MHASSAN1 | Approved | |
| 03/13/2018 | ELECTRIC - FINAL | MHASSAN1 | Approved | |
| 03/13/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | WAY BEYOND THIS AT THE TIME OF MY INSPECTION |
| 03/14/2018 | BUILDING - FINAL | AR | Approved | REVISION COMPLETED |
| 03/14/2018 | BUILDING - FINAL | MHASSAN1 | Approved | APPROVAL PENDING APPROVED REVISION |