Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
10/26/2017
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LENN4062 T16-M0067
Contractors:
  • LENNAR ARIZONA CONSTRUCTION INC

Permit Reviews

Permit Number - T17CM08054
Permit Status: Final
Permit Description: SFR LENN4062 T16-M0067
Start Date Submittal Complete Date Status  
10/26/2017 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 10/26/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM08054
Permit Status: Final
Permit Description: SFR LENN4062 T16-M0067
Total Outstanding Activity Conditions - 1
Date Name
10/26/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM08054
Permit Description: SFR LENN4062 T16-M0067
Total Completed Inspections - 27
Date Description Inspector Results Comments
11/21/2017 PLUMBING - SEWER HCS CONNECT NORTH Approved
11/21/2017 PLUMBING - YARD WTR LINE/TEST NORTH Approved
11/22/2017 PLUMBING - ROUGH, SOIL TVALENC1 Approved IVRS - Inspection :*
12/04/2017 ELECTRIC - UFER ESTEVEN1 Approved
12/04/2017 ELECTRIC - UNDERGROUND ESTEVEN1 Approved APPROVED
12/04/2017 BUILDING PRE-SLAB ESTEVEN1 Approved APPROVED
12/04/2017 EXCAVATION/LAYOUT REBAR & ZON ESTEVEN1 Approved APPROVED
01/04/2018 ROOF NAILING TVALENC1 Approved IVRS - Inspection :*
01/04/2018 EXT METAL CLIPS/EXT SHEATHING TVALENC1 Approved IVRS - Inspection :*
01/16/2018 ELECTRIC - CONSTRUCTION POWER rbaldwin Approved
01/16/2018 ELECTRIC - CABLE DROP rbaldwin Approved
01/17/2018 TEP CLEARANCE - AM RBALDWIN Approved TEC
02/02/2018 MECHANICAL - INTERMEDIATE MHASSAN1 Approved
02/02/2018 PLUMBING - GAS PRESSURE TEST MHASSAN1 Approved
02/02/2018 PLUMBING - INTERMEDIATE MHASSAN1 Approved
02/02/2018 ELECTRIC - INTERMEDIATE MHASSAN1 Approved
02/02/2018 U VALUE FOR WINDOW MHASSAN1 Approved
02/02/2018 STUCCO MESH MHASSAN1 Approved
02/06/2018 FRAMING MHASSAN1 Approved
02/15/2018 SHEET ROCK NAILING MHASSAN1 Approved
04/11/2018 GAS CLEARANCE DFLORES Approved
04/11/2018 PLUMBING - PROGRESS DFLORES2 Approved CLEAR SW GAS
04/23/2018 MECHANICAL - FINAL DFLORES2 Approved
04/23/2018 PLUMBING - FINAL DFLORES2 Approved
04/23/2018 OUTDOOR LIGHTING FINAL DFLORES2 Approved
04/23/2018 ELECTRIC - FINAL DFLORES2 Approved
04/24/2018 BUILDING - FINAL DFLORES2 Approved