Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM08047
Permit Details
Apply Date:
10/26/2017
Applicant:
K B HOME OF TUCSON *APA*
Description:
SFR PLAN1231 T17-M0023
Contractors:
- K B HOME OF TUCSON *APA*
Permit Reviews
Permit Number - T17CM08047
Permit Status: Final
Permit Description: SFR PLAN1231 T17-M0023
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/26/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 10/26/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM08047
Permit Status: Final
Permit Description: SFR PLAN1231 T17-M0023
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/26/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM08047
Permit Description: SFR PLAN1231 T17-M0023
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/01/2017 | PLUMBING - SEWER HCS CONNECT | BBENEDO1 | Approved | IVRS - Inspection :* |
11/01/2017 | PLUMBING - YARD WTR LINE/TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
11/01/2017 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
11/13/2017 | ELECTRIC - UNDERGROUND | BBENEDO1 | Approved | IVRS - Inspection :* |
11/13/2017 | ELECTRIC - UFER | BBENEDO1 | Approved | IVRS - Inspection :* |
11/13/2017 | BUILDING PRE-SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
11/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDO1 | Approved | IVRS - Inspection :* |
12/05/2017 | ROOF NAILING | BBENEDO1 | Approved | IVRS - Inspection :* |
12/05/2017 | EXT METAL CLIPS/EXT SHEATHING | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | U VALUE FOR WINDOW | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | STUCCO MESH | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | PLUMBING - GAS PRESSURE TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | PLUMBING - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | ELECTRIC - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | FRAMING | BBENEDO1 | Approved | IVRS - Inspection :* |
12/22/2017 | MECHANICAL - ABOVE CEILING | BBENEDO1 | Approved | IVRS - Inspection :* |
12/22/2017 | BUILDING ABOVE CEILING | BBENEDO1 | Approved | IVRS - Inspection :* |
12/22/2017 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
01/02/2018 | ELECTRIC - CONSTRUCTION POWER | NORTH | Approved | |
01/02/2018 | ELECTRIC - CABLE DROP | NORTH | Approved | |
01/02/2018 | SHEET ROCK NAILING | NORTH | Approved | |
02/16/2018 | GAS CLEARANCE | RGREENE | Approved | |
02/16/2018 | OUTDOOR LIGHTING FINAL | RGREENE1 | Approved | |
02/27/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | |
02/27/2018 | PLUMBING - FINAL | DFLORES2 | Approved | |
02/27/2018 | ELECTRIC - FINAL | DFLORES2 | Approved | |
02/27/2018 | BUILDING - FINAL | DFLORES2 | Approved |