Permit: T17CM07924
Permit Details
Apply Date:
10/20/2017
Applicant:
MCQUILLEN, THOMAS
Description:
CATH LAB
Architects:
- MCQUILLEN, THOMAS
Contractors:
- M J I COMPANY L L C
Permit Reviews
Permit Number - T17CM07924
Permit Status: L of c
Permit Description: CATH LAB
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/20/2017 | COMMERCIAL - TI | 03/20/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07924
Permit Status: L of c
Permit Description: CATH LAB
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/20/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM07924
Permit Description: CATH LAB
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/20/2017 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
10/20/2017 | PLUMBING - FINAL | RSHERRY | Approved | WATER CHLORINATION REPORT AND MEDICAL GAS REPORT REQUIRED |
04/13/2018 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
04/13/2018 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | |
04/13/2018 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
04/18/2018 | FRAMING | JBURGE | Approved | CONTROL ROOM COMPLETE - OK TO SHEET ROCK THROUGHOUT. |
05/04/2018 | MECHANICAL - HYDRONIC PIPING | JBURGE | Approved | INSULATED IN CONTROL ROOM. |
05/04/2018 | PLUMBING - PROGRESS | JBURGE | Approved | |
05/04/2018 | PLUMBING - MEDICAL GAS/TEST | JBURGE | Approved | GAS LINES FOR WAGD, VACCUUM, MEDICAL AIR OXYGEN, NITROUS OXIDE ALL TESTED AT 100 PSI. |
05/04/2018 | PLUMBING - MD GAS/PRECONST MTG | JBURGE | Approved | |
05/04/2018 | BUILDING - PROGRESS | JBURGE | Approved | |
05/25/2018 | ELECTRIC - FINAL | JBURGE | Approved | |
05/25/2018 | FIRE SPKLR - FINAL | jvincent | Approved | |
05/29/2018 | ENGINEERING - FINAL | MRUSSO | Approved | |
06/07/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
06/07/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
06/11/2018 | BUILDING - FINAL | JBURGE | Approved | BACTERIA TESTING AND AIR BALANCE TO BE TURNED IN AT REQUEST FOR LETTER OF COMPLETION. |
06/13/2018 | PLUMBING - ABOVE CEILING | JBURGE | Approved | |
06/13/2018 | SHEET ROCK NAILING | JBURGE | Approved | |
06/13/2018 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | |
06/13/2018 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
06/13/2018 | PLUMBING - MEDICAL GAS/FINAL | RSHERRY | Approved | MEDICAL GAS REPORT RECIEVED |