Permit: T17CM07732
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
3069 N DASYLIRION DR
Address NEW:
3069 N DASYLIRION DR
Apply Date:
10/12/2017
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Description:
SFR PE162117 T17-M0047
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Permit Reviews
Permit Number - T17CM07732
Permit Status: C of o
Permit Description: SFR PE162117 T17-M0047
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/12/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 10/13/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07732
Permit Status: C of o
Permit Description: SFR PE162117 T17-M0047
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/12/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM07732
Permit Description: SFR PE162117 T17-M0047
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/23/2017 | PLUMBING - SEWER HCS CONNECT | NORTH | Approved | |
| 10/23/2017 | PLUMBING - YARD WTR LINE/TEST | NORTH | Approved | |
| 10/23/2017 | PLUMBING - ROUGH, SOIL | NORTH | Approved | |
| 10/30/2017 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | APPROVED |
| 10/30/2017 | BUILDING PRE-SLAB | ESTEVENS | Approved | APPROVED |
| 10/30/2017 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | APPROVED |
| 11/17/2017 | ROOF NAILING | BSTEVENS | Approved | |
| 11/17/2017 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | |
| 11/21/2017 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | |
| 11/21/2017 | ELECTRIC - CABLE DROP | BSTEVENS | Approved | |
| 11/21/2017 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 11/22/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | TMPP |
| 12/04/2017 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
| 12/04/2017 | FIREWALL/FIREBARRIER/FIRESTOP | BSTEVENS | Approved | |
| 12/04/2017 | STUCCO MESH | BSTEVENS | Approved | |
| 12/05/2017 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
| 12/05/2017 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | |
| 12/05/2017 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | |
| 12/05/2017 | FRAMING | BSTEVENS | Approved | |
| 12/12/2017 | BUILDING - FINAL | BSTEVENS | Approved | |
| 12/13/2017 | SHEET ROCK NAILING | BSTEVENS | Approved | |
| 01/23/2018 | MECHANICAL - FINAL | JBURGE | Approved | |
| 01/23/2018 | PLUMBING - FINAL | JBURGE | Approved | |
| 01/23/2018 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 01/23/2018 | ELECTRIC - FINAL | JBURGE | Approved | |
| 01/24/2018 | GAS CLEARANCE | JBURGE | Approved |