Permit: T17CM07657
Permit Details
Apply Date:
10/10/2017
Applicant:
SONORAN DESIGN GROUP
Description:
SFR SDGM1606 T17-M006
Architects:
- SONORAN DESIGN GROUP
Permit Reviews
Permit Number - T17CM07657
Permit Status: C of o
Permit Description: SFR SDGM1606 T17-M006
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/10/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 10/11/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07657
Permit Status: C of o
Permit Description: SFR SDGM1606 T17-M006
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/10/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM07657
Permit Description: SFR SDGM1606 T17-M006
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2017 | PLUMBING - SEWER HCS CONNECT | RGREENE | Approved | |
| 11/06/2017 | PLUMBING - ROUGH, SOIL | RGREENE | Approved | |
| 11/07/2017 | BUILDING PRE-SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
| 11/07/2017 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDO1 | Approved | IVRS - Inspection :* |
| 11/08/2017 | BUILDING - FINAL | pyg | Approved | Do not final until RWRD has issued an authorization to discharge. |
| 12/15/2017 | EXT METAL CLIPS/EXT SHEATHING | mramber1 | Approved | |
| 12/15/2017 | ROOF NAILING | mramber1 | Approved | |
| 12/15/2017 | FRAMING | mramber1 | Approved | |
| 12/15/2017 | ELECTRIC - UFER | mramber1 | Approved | provide 2 ground rods |
| 12/15/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
| 12/15/2017 | PLUMBING - GAS PRESSURE TEST | mramber1 | Approved | |
| 12/20/2017 | MECHANICAL - INTERMEDIATE | rbaldwin | Approved | |
| 12/22/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
| 01/10/2018 | STUCCO MESH | mramber1 | Approved | |
| 01/10/2018 | U VALUE FOR WINDOW | mramber1 | Approved | |
| 03/01/2018 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
| 03/01/2018 | ELECTRIC - UNDERGROUND | mramber1 | Approved | |
| 04/09/2018 | PLUMBING - PROGRESS | RBALDWIN | Approved | OK TO SET GAS METER |
| 04/09/2018 | PLUMBING - YARD WTR LINE/TEST | RBALDWIN | Approved | OK TO SET GAS METER |
| 04/09/2018 | OUTDOOR LIGHTING FINAL | RBALDWIN | Approved | OK TO SET GAS METER |
| 04/09/2018 | ELECTRIC - CONSTRUCTION POWER | RBALDWIN | Approved | OK TO SET GAS METER |
| 04/09/2018 | ELECTRIC - CABLE DROP | RBALDWIN | Approved | OK TO SET GAS METER |
| 04/11/2018 | GAS CLEARANCE | RBALDWIN | Approved | |
| 04/25/2018 | MECHANICAL - FINAL | rbaldwin | Approved | |
| 04/25/2018 | PLUMBING - FINAL | rbaldwin | Approved | |
| 04/25/2018 | ELECTRIC - FINAL | rbaldwin | Approved |