Permit: T17CM07425
Permit Details
Apply Date:
09/28/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: BARBER SHOP
Contractors:
- GALILEO CONSTRUCTION L L C
Permit Reviews
Permit Number - T17CM07425
Permit Status: Expired
Permit Description: TI: BARBER SHOP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/28/2017 | COMMERCIAL - TI | 10/11/2017 | COMPLETED |
10/11/2017 | RESUBMITTAL | 11/21/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07425
Permit Status: Expired
Permit Description: TI: BARBER SHOP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/28/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T17CM07425
Permite Description: TI: BARBER SHOP
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
FIREWALL/FIREBARRIER/FIRESTOP | N/A | Not Inspected | ||
01/12/2018 | BUILDING - FINAL | N/A | Partial Approval | PENDING OTHER INSPECTIONS |
01/12/2018 | CERTIFICATE OF OCCUPANCY | N/A | Partial Approval | PENDING OTHER INSPECTIONS |
Completed Inspections
Permit Status: Expired
Permit Number: T17CM07425
Permit Description: TI: BARBER SHOP
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/08/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | BARBER SHOP AREA |
12/08/2017 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
12/08/2017 | FRAMING | ESTEVEN1 | Approved | APPROVED |
12/08/2017 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
01/09/2018 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
01/09/2018 | ELECTRIC - SERVICE UPGRADE | ESTEVEN1 | Approved | APPROVED |
01/09/2018 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
01/09/2018 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
01/11/2018 | ENGINEERING - FINAL | MRUSSO | Approved | |
01/12/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
01/12/2018 | PLUMBING - PRE SLAB | ESTEVEN1 | Approved | |
01/12/2018 | ELECTRIC - FINAL | ESTEVEN1 | Approved | APPROVED |
01/16/2018 | FIRE - FINAL | JPEELDAVIS | Approved | OK for TCO needs to add fire alarm for second phase. |
01/16/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | Needs to add a fire alarm. In agreement with Clayton ok for TCO. Needs fire alarm prior to calling in fire final on second phase. |
01/16/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
01/17/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETE |
12/28/2018 | PLUMBING - FINAL | ESTEVEN1 | Approved | WATER CHLORINATION REPORT NEEDED |