Permit: T17CM07219
Permit Details
Apply Date:
09/19/2017
Applicant:
BRIGHT, RICK LANE
Description:
SFR 1242CIM T17-M0044
Architects:
- BRIGHT, RICK LANE
Contractors:
- CONTRACTCO INC
Permit Reviews
Permit Number - T17CM07219
Permit Status: C of o
Permit Description: SFR 1242CIM T17-M0044
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/19/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 10/05/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07219
Permit Status: C of o
Permit Description: SFR 1242CIM T17-M0044
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/19/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM07219
Permit Description: SFR 1242CIM T17-M0044
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/22/2017 | PLUMBING - SEWER HCS CONNECT | RGREENE1 | Approved | |
12/22/2017 | PLUMBING - YARD WTR LINE/TEST | RGREENE1 | Approved | |
12/22/2017 | PLUMBING - ROUGH, SOIL | RGREENE1 | Approved | |
01/08/2018 | ELECTRIC - UNDERGROUND | rbaldwin | Approved | |
01/08/2018 | ELECTRIC - UFER | rbaldwin | Approved | |
01/08/2018 | BUILDING PRE-SLAB | rbaldwin | Approved | |
01/08/2018 | EXCAVATION/LAYOUT REBAR & ZON | rbaldwin | Approved | |
07/02/2018 | ROOF NAILING | mramber1 | Approved | roof too steep for safe inspection, contractor verified proper nailing porch/storage party walls only |
07/02/2018 | FRAMING | mramber1 | Approved | roof too steep for safe inspection, contractor verified proper nailing porch/ storage party walls only |
08/09/2018 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
09/27/2018 | ELECTRIC - CONSTRUCTION POWER | MRAMBER1 | Approved | IVRS - Inspection :* |
09/27/2018 | ELECTRIC - CABLE DROP | MRAMBER1 | Approved | IVRS - Inspection :* |
09/28/2018 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
01/04/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
01/04/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | |
01/04/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
01/04/2019 | U VALUE FOR WINDOW | MHASSAN | Approved | |
01/04/2019 | STUCCO MESH | MHASSAN | Approved | |
03/18/2019 | BUILDING - FINAL | MHASSAN | Approved | |
03/18/2019 | MECHANICAL - FINAL | MHASSAN | Approved | |
03/18/2019 | PLUMBING - FINAL | MHASSAN | Approved | |
03/18/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
03/18/2019 | ELECTRIC - FINAL | MHASSAN | Approved |