Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM07156
Permit Details
Apply Date:
09/18/2017
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT90817 T17-M0036
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T17CM07156
Permit Status: Final
Permit Description: SFR RICHT90817 T17-M0036
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/18/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 09/20/2017 | COMPLETED |
09/25/2017 | REVISION - - 1ST | 09/26/2017 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T17CM07156
Permit Status: Final
Permit Description: SFR RICHT90817 T17-M0036
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/18/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM07156
Permit Description: SFR RICHT90817 T17-M0036
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/25/2017 | PLUMBING - YARD WTR LINE/TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
09/25/2017 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
09/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | NORTH | Approved | |
09/27/2017 | ELECTRIC - UNDERGROUND | NORTH | Approved | |
10/04/2017 | ROOF NAILING | BBENEDO1 | Approved | IVRS - Inspection :* |
10/04/2017 | EXT METAL CLIPS/EXT SHEATHING | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | ELECTRIC - CONSTRUCTION POWER | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | ELECTRIC - CABLE DROP | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | U VALUE FOR WINDOW | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | STUCCO MESH | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | BUILDING PRE-SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | PLUMBING - GAS PRESSURE TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | PLUMBING - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | ELECTRIC - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
10/06/2017 | FRAMING | BBENEDO1 | Approved | IVRS - Inspection :* |
10/09/2017 | OUTDOOR LIGHTING FINAL | benedon | Approved | eco |
10/20/2017 | SHEET ROCK NAILING | BBENEDO1 | Approved | IVRS - Inspection :* |
12/07/2017 | PLUMBING - SEWER HCS CONNECT | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | BUILDING - FINAL | BBENEDO1 | Approved | Inspector has no prob with TCO as noted below. |
12/21/2017 | MECHANICAL - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | PLUMBING - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | ELECTRIC - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
12/21/2017 | ELECTRIC - UFER | BBENEDO1 | Approved | IVRS - Inspection :* |