Permit: T17CM06998
Permit Details
Apply Date:
09/13/2017
Applicant:
PULTE DEVELOPMENT CORPORATION ,
Description:
SFR PULT5532-1 T16-M0045
Contractors:
- PULTE DEVELOPMENT CORPORATION ,
- PULTE HOME CORP AZ *APA*
Outstanding Activity Conditions
Permit Number - T17CM06998
Permit Status: Final
Permit Description: SFR PULT5532-1 T16-M0045
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/13/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM06998
Permit Description: SFR PULT5532-1 T16-M0045
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2017 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 12/01/2017 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 12/01/2017 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | |
| 12/08/2017 | ELECTRIC - UFER | NORTH | Approved | REBAR ONLY |
| 12/08/2017 | ELECTRIC - UNDERGROUND | NORTH | Approved | |
| 12/08/2017 | BUILDING PRE-SLAB | NORTH | Approved | |
| 12/08/2017 | EXCAVATION/LAYOUT REBAR & ZON | NORTH | Approved | |
| 12/28/2017 | ROOF NAILING | NORTH | Approved | |
| 12/28/2017 | EXT METAL CLIPS/EXT SHEATHING | NORTH | Approved | |
| 01/09/2018 | ELECTRIC - CABLE DROP | TVALENC1 | Approved | IVRS - Inspection :* CLEAR ELECTRIC ECO |
| 01/09/2018 | ELECTRIC - CONSTRUCTION POWER | TVALENC1 | Approved | IVRS - Inspection :* |
| 01/10/2018 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
| 02/09/2018 | MECHANICAL - INTERMEDIATE | MHASSAN1 | Approved | |
| 02/09/2018 | PLUMBING - GAS PRESSURE TEST | MHASSAN1 | Approved | |
| 02/09/2018 | PLUMBING - INTERMEDIATE | MHASSAN1 | Approved | |
| 02/09/2018 | ELECTRIC - INTERMEDIATE | MHASSAN1 | Approved | |
| 02/09/2018 | U VALUE FOR WINDOW | MHASSAN1 | Approved | |
| 02/09/2018 | STUCCO MESH | MHASSAN1 | Approved | |
| 02/09/2018 | FRAMING | MHASSAN1 | Approved | DO NOT COVER SPRINKLER LINES UNTIL FIRE DEPT. INSPECTION |
| 02/26/2018 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/11/2018 | PLUMBING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* CLEAR GAS METER |
| 04/12/2018 | GAS CLEARANCE | TVALENCIA | Approved | |
| 04/26/2018 | MECHANICAL - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | OUTDOOR LIGHTING FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | BUILDING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |