Permit: T17CM06312
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
6608 E VIA PAMPAS MORENAS
Address NEW:
6608 E VIA PAMPAS MORENAS
Apply Date:
08/16/2017
Applicant:
MERITAGE HOMES
Description:
SFR PLAN1610 T16-M0011
Contractors:
- MERITAGE HOMES
- MERITAGE HOMES CONSTRUCTION INC *** APA***
Outstanding Activity Conditions
Permit Number - T17CM06312
Permit Status: Final
Permit Description: SFR PLAN1610 T16-M0011
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/16/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM06312
Permit Description: SFR PLAN1610 T16-M0011
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2017 | PLUMBING - SEWER HCS CONNECT | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/06/2017 | PLUMBING - YARD WTR LINE/TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/06/2017 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/06/2017 | SITE - SEWER | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/11/2017 | PLUMBING - PRE SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/11/2017 | ELECTRIC - UNDERGROUND | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/11/2017 | ELECTRIC - UFER | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/11/2017 | BUILDING PRE-SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/10/2017 | ROOF NAILING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/10/2017 | EXT METAL CLIPS/EXT SHEATHING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/19/2017 | ELECTRIC - CABLE DROP | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/20/2017 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
| 10/27/2017 | U VALUE FOR WINDOW | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/27/2017 | STUCCO MESH | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/27/2017 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/27/2017 | PLUMBING - GAS PRESSURE TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/27/2017 | PLUMBING - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/27/2017 | ELECTRIC - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 10/27/2017 | FRAMING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 11/13/2017 | SHEET ROCK NAILING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 12/28/2017 | PLUMBING - GAS PRESS TEST FNL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 12/29/2017 | GAS CLEARANCE | BBENEDON | Approved | |
| 01/02/2018 | MECHANICAL - FINAL | NORTH | Approved | |
| 01/02/2018 | PLUMBING - FINAL | NORTH | Approved | |
| 01/02/2018 | ELECTRIC - FINAL | NORTH | Approved | |
| 01/02/2018 | BUILDING - FINAL | NORTH | Approved |