Permit: T17CM06310
Permit Details
Apply Date:
08/16/2017
Applicant:
BREAN KEVIN E & MEJIAS-BREAN LISA A CP/RS
Description:
NEW SFR
Permit Reviews
Permit Number - T17CM06310
Permit Status: Final
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/16/2017 | PLANS OK TO SUBMIT - RES | 08/16/2017 | COMPLETED |
| 08/16/2017 | RESIDENTIAL - BLDG/WWM | 09/07/2017 | COMPLETED |
| 09/08/2017 | RESUBMITTAL | 09/12/2017 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T17CM06310
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/16/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM06310
Permit Description: NEW SFR
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/18/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | IVRS - Inspection :* |
| 10/02/2018 | PLUMBING - PRE SLAB | MHASSAN | Approved | |
| 10/02/2018 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 10/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 11/02/2018 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 11/02/2018 | SHEET ROCK NAILING | DQUINN | Approved | |
| 11/02/2018 | FRAMING | DQUINN | Approved | Parapet ledger clips ok to cover |
| 11/06/2018 | ROOF NAILING | MHASSAN | Approved | need truss calcs verified before full approval. Okay to cover sheathing. |
| 04/04/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | |
| 04/04/2019 | MECHANICAL - INTERMEDIATE | GWEST | Approved | |
| 04/04/2019 | PLUMBING - INTERMEDIATE | GWEST | Approved | |
| 04/24/2019 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | Gas piping in walls OK to cover. |
| 07/02/2019 | TEP CLEARANCE - PM | MRAMBER | Approved | CODE ECO This is new construction, Not an upgrade. |
| 07/02/2019 | ELECTRIC - UFER | MRAMBER | Approved | |
| 07/02/2019 | ELECTRIC - SERVICE UPGRADE | MRAMBER | Approved | ECO OK to clear. This is new construction, Not an upgrade. |
| 08/29/2019 | BUILDING - FINAL | RCHANDLER | Approved | |
| 08/29/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
| 08/29/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 08/29/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 08/29/2019 | GAS CLEARANCE | RCHANDLER | Approved | |
| 08/29/2019 | PLUMBING - GAS PRESS TEST FNL | RCHANDLER | Approved | Clearance SWG OK to connect. |
| 08/29/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 08/29/2019 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | |
| 08/29/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved |