Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
4722 E BROADWAY BL
Apply Date:
08/11/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
GYMNASIUM
Contractors:
  • CHESTNUT BUILDING & DESIGN INC

Permit Reviews

Permit Number - T17CM06203
Permit Status: C of o
Permit Description: GYMNASIUM
Start Date Submittal Complete Date Status  
08/11/2017 PLANS OK TO SUBMIT - COMM 08/11/2017 COMPLETED Review Details
08/23/2017 3RD PARTY REVIEW - COMMERCIAL TI 09/15/2017 COMPLETED Review Details
09/15/2017 3RD PARTY REVIEW - COMMERCIAL 09/28/2017 COMPLETED Review Details
09/28/2017 RESUBMITTAL 10/04/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM06203
Permit Status: C of o
Permit Description: GYMNASIUM
Total Outstanding Activity Conditions - 1
Date Name
08/11/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T17CM06203
Permit Description: GYMNASIUM
Total Completed Inspections - 26
Date Description Inspector Results Comments
10/05/2017 PLUMBING - ROUGH, SOIL DQUINN Approved
10/10/2017 BUILDING PRE-SLAB RGREENE1 Approved
10/26/2017 MECHANICAL - INTERMEDIATE BBENEDO1 Approved IVRS - Inspection :*
11/02/2017 PLUMBING - ABOVE CEILING RGREENE Approved
11/02/2017 ELECTRIC - INTERMEDIATE RGREENE Approved
11/08/2017 PLUMBING - INTERMEDIATE RGREENE Approved ALL GATES WERE LOCKED: COULD NOT GAIN ACCESS
11/08/2017 FRAMING RGREENE Approved CHICAGO GRID SYSTEM INSTALLED PER MANUFACTURERS INSTALLATION INSTRUCTIONS
11/15/2017 SHEET ROCK NAILING RGREENE1 Approved
11/29/2017 U VALUE FOR WINDOW RGREENE1 Approved
11/29/2017 EXCAVATION/LAYOUT REBAR & ZON RGREENE1 Approved
12/07/2017 BUILDING ABOVE CEILING NORTH Approved
12/07/2017 ELECTRIC - ABOVE CEILING NORTH Approved
12/07/2017 PLUMBING - GAS PRESSURE TEST NORTH Approved
12/07/2017 MECHANICAL - ABOVE CEILING NORTH Approved
12/08/2017 GAS CLEARANCE BNORTH Approved
12/11/2017 PLUMBING - GAS PRESS TEST FNL RGREENE1 Approved
12/20/2017 FIRE SPKLR - FINAL JPEELDAVIS Approved
12/21/2017 CERTIFICATE OF OCCUPANCY RYAN Approved
12/21/2017 BUILDING - FINAL RYAN Approved PENDING CHLORINATION REPORT
PENDING AIR BALANCE REPORT
12/21/2017 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETE
12/22/2017 FIRE - ALARM FINAL gdauria1 Approved
12/22/2017 FIRE - FINAL gdauria1 Approved
12/28/2017 ENGINEERING - FINAL MRUSSO Approved
01/10/2018 OUTDOOR LIGHTING FINAL RYAN Approved
01/10/2018 ELECTRIC - FINAL RYAN Approved
01/10/2018 PLUMBING - FINAL RYAN Approved