Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM06203
Permit Details
Apply Date:
08/11/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
GYMNASIUM
Contractors:
- CHESTNUT BUILDING & DESIGN INC
Permit Reviews
Permit Number - T17CM06203
Permit Status: C of o
Permit Description: GYMNASIUM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/11/2017 | PLANS OK TO SUBMIT - COMM | 08/11/2017 | COMPLETED |
08/23/2017 | 3RD PARTY REVIEW - COMMERCIAL TI | 09/15/2017 | COMPLETED |
09/15/2017 | 3RD PARTY REVIEW - COMMERCIAL | 09/28/2017 | COMPLETED |
09/28/2017 | RESUBMITTAL | 10/04/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM06203
Permit Status: C of o
Permit Description: GYMNASIUM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/11/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM06203
Permit Description: GYMNASIUM
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/05/2017 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
10/10/2017 | BUILDING PRE-SLAB | RGREENE1 | Approved | |
10/26/2017 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
11/02/2017 | PLUMBING - ABOVE CEILING | RGREENE | Approved | |
11/02/2017 | ELECTRIC - INTERMEDIATE | RGREENE | Approved | |
11/08/2017 | PLUMBING - INTERMEDIATE | RGREENE | Approved | ALL GATES WERE LOCKED: COULD NOT GAIN ACCESS |
11/08/2017 | FRAMING | RGREENE | Approved | CHICAGO GRID SYSTEM INSTALLED PER MANUFACTURERS INSTALLATION INSTRUCTIONS |
11/15/2017 | SHEET ROCK NAILING | RGREENE1 | Approved | |
11/29/2017 | U VALUE FOR WINDOW | RGREENE1 | Approved | |
11/29/2017 | EXCAVATION/LAYOUT REBAR & ZON | RGREENE1 | Approved | |
12/07/2017 | BUILDING ABOVE CEILING | NORTH | Approved | |
12/07/2017 | ELECTRIC - ABOVE CEILING | NORTH | Approved | |
12/07/2017 | PLUMBING - GAS PRESSURE TEST | NORTH | Approved | |
12/07/2017 | MECHANICAL - ABOVE CEILING | NORTH | Approved | |
12/08/2017 | GAS CLEARANCE | BNORTH | Approved | |
12/11/2017 | PLUMBING - GAS PRESS TEST FNL | RGREENE1 | Approved | |
12/20/2017 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
12/21/2017 | CERTIFICATE OF OCCUPANCY | RYAN | Approved | |
12/21/2017 | BUILDING - FINAL | RYAN | Approved | PENDING CHLORINATION REPORT PENDING AIR BALANCE REPORT |
12/21/2017 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETE |
12/22/2017 | FIRE - ALARM FINAL | gdauria1 | Approved | |
12/22/2017 | FIRE - FINAL | gdauria1 | Approved | |
12/28/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
01/10/2018 | OUTDOOR LIGHTING FINAL | RYAN | Approved | |
01/10/2018 | ELECTRIC - FINAL | RYAN | Approved | |
01/10/2018 | PLUMBING - FINAL | RYAN | Approved |