Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM06168
Permit Details
Apply Date:
08/10/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: MEDICAL
Architects:
- BOLLARD, MARK EDWARD
Contractors:
- CHESTNUT BUILDING & DESIGN INC
Permit Reviews
Permit Number - T17CM06168
Permit Status: C of o
Permit Description: TI: MEDICAL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/10/2017 | COMMERCIAL - TI | 09/28/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM06168
Permit Status: C of o
Permit Description: TI: MEDICAL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/10/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM06168
Permit Description: TI: MEDICAL
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/18/2017 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
10/31/2017 | SHEET ROCK NAILING | BSTEVENS | Approved | |
11/21/2017 | MECHANICAL - ABOVE CEILING | BSTEVENS | Approved | |
11/21/2017 | PLUMBING - ABOVE CEILING | BSTEVENS | Approved | |
11/21/2017 | ELECTRIC - ABOVE CEILING | BSTEVENS | Approved | |
11/21/2017 | BUILDING ABOVE CEILING | BSTEVENS | Approved | |
12/05/2017 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
12/08/2017 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
12/08/2017 | PLUMBING - FINAL | BSTEVENS | Approved | |
12/08/2017 | PLUMBING - PROGRESS | BSTEVENS | Approved | |
12/08/2017 | ELECTRIC - FINAL | BSTEVENS | Approved | |
12/08/2017 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
12/08/2017 | BUILDING - PROGRESS | BSTEVENS | Approved | |
12/08/2017 | FRAMING | BSTEVENS | Approved | |
12/11/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
12/14/2017 | FIRE - FINAL | jdonovan | Approved | |
12/14/2017 | FIRE - ALARM FINAL | jdonovan | Approved | |
12/15/2017 | BUILDING - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETE |
12/15/2017 | MECHANICAL - FINAL | RSHERRY | Approved | EXHAUST SYSTEM REPAIRED. REVIEW OF AIR BALANCE REPORT COMPLETE |
12/18/2017 | CERTIFICATE OF OCCUPANCY | RSHERRY | Approved | ROBERT SHERRY EMAILED APPROVAL TO CUSTOMER. EMAIL SENT TO RECORDS. |