Permit: T17CM05585
Permit Details
Apply Date:
07/21/2017
Applicant:
KRZYSIK, HENRY JOSEPH JR
Description:
SFR MODEL1349 T17-M0037
Architects:
- KRZYSIK, HENRY JOSEPH JR
Permit Reviews
Permit Number - T17CM05585
Permit Status: Final
Permit Description: SFR MODEL1349 T17-M0037
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/21/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 07/21/2017 | COMPLETED |
| 11/24/2017 | REVISION - - 1ST | 12/04/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM05585
Permit Status: Final
Permit Description: SFR MODEL1349 T17-M0037
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/21/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM05585
Permit Description: SFR MODEL1349 T17-M0037
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/24/2017 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 08/24/2017 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 09/07/2017 | BUILDING PRE-SLAB | RCAMACHO | Approved | EXCEPT HOME INCLUSIVE ENTRY |
| 09/07/2017 | PLUMBING - PRE SLAB | RCAMACHO | Approved | |
| 09/22/2017 | ELECTRIC - UFER | DQUINN | Approved | |
| 09/22/2017 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | FOR CABLE DROP AND POWER |
| 09/25/2017 | TEP CLEARANCE - AM | QUINN | Approved | ECO |
| 11/17/2017 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | |
| 01/22/2018 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN1 | Approved | |
| 04/05/2018 | ROOF NAILING | RCAMACHO | Approved | PROVIDE 1/2" FOR DEFLECTION 2PT BEARING A/2, A/3 AND A/4 TRUSSES |
| 08/10/2018 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
| 08/10/2018 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | |
| 08/10/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
| 08/10/2018 | MECHANICAL - INTERMEDIATE | RCAMACH1 | Approved | IVRS - Inspection :* |
| 08/10/2018 | PLUMBING - INTERMEDIATE | RCAMACH1 | Approved | IVRS - Inspection :* |
| 08/10/2018 | ELECTRIC - INTERMEDIATE | RCAMACH1 | Approved | IVRS - Inspection :* |
| 08/14/2018 | FRAMING | mramber1 | Approved | |
| 08/14/2018 | STUCCO MESH | mramber1 | Approved | |
| 09/05/2018 | SHEET ROCK NAILING | RCAMACH1 | Approved | IVRS - Inspection :* |
| 09/05/2018 | U VALUE FOR WINDOW | RCAMACH1 | Approved | IVRS - Inspection :* |
| 02/26/2019 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | APPROVAL UPON 2090 BY RCAMACHO |
| 02/26/2019 | ELECTRIC - SERVICE UPGRADE | RCAMACHO | Approved | APPROVAL UPON 2090 BY RCAMACHO |
| 02/26/2019 | MECHANICAL - FINAL | RCAMACHO | Approved | |
| 02/26/2019 | PLUMBING - FINAL | RCAMACHO | Approved | |
| 02/26/2019 | ELECTRIC - FINAL | RCAMACHO | Approved | |
| 02/26/2019 | BUILDING - FINAL | RCAMACHO | Approved | |
| 02/26/2019 | MECHANICAL - PROGRESS | RCAMACHO | Approved | |
| 02/26/2019 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | |
| 02/26/2019 | PLUMBING - PROGRESS | RCAMACHO | Approved | |
| 02/26/2019 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
| 02/26/2019 | ELECTRIC - PROGRESS | RCAMACHO | Approved | |
| 02/26/2019 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
| 02/26/2019 | BUILDING - PROGRESS | RCAMACHO | Approved | |
| 02/26/2019 | BUILDING ABOVE CEILING | RCAMACHO | Approved |