Permit: T17CM05260
Permit Details
Apply Date:
07/10/2017
Applicant:
RENE MARTINEZ FLORES
Description:
DEMO CARPORT & REBUILD/EXPAND BEDROOM
Permit Reviews
Permit Number - T17CM05260
Permit Status: Final
Permit Description: DEMO CARPORT & REBUILD/EXPAND BEDROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/10/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 07/10/2017 | COMPLETED |
| 07/10/2017 | RESIDENTIAL - BLDG/WWM | 08/14/2017 | COMPLETED |
| 08/14/2017 | RESUBMITTAL | 09/05/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM05260
Permit Status: Final
Permit Description: DEMO CARPORT & REBUILD/EXPAND BEDROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/10/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM05260
Permit Description: DEMO CARPORT & REBUILD/EXPAND BEDROOM
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/08/2017 | PLUMBING - ROUGH, SOIL | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/08/2017 | PLUMBING - ROUGH, SOIL | JMILITE1 | Approved | SYSTEM NOT UNDER TEST. |
| 10/02/2017 | BUILDING PRE-SLAB | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/02/2017 | EXCAVATION/LAYOUT REBAR & ZON | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/24/2017 | REINFORCED MASONRY PRE-GROUT | NORTH | Approved | |
| 03/29/2018 | MECHANICAL - INTERMEDIATE | DFLORES2 | Approved | |
| 03/29/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | |
| 03/29/2018 | ELECTRIC - INTERMEDIATE | DFLORES2 | Approved | |
| 03/29/2018 | U VALUE FOR WINDOW | DFLORES2 | Approved | |
| 03/29/2018 | FRAMING | DFLORES2 | Approved | |
| 03/29/2018 | ROOF NAILING | DFLORES2 | Approved | |
| 01/25/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 01/25/2019 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | |
| 01/25/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 01/28/2019 | GAS CLEARANCE | RCHANDLER | Approved | |
| 02/25/2019 | MECHANICAL - FINAL | GWEST | Approved | |
| 03/29/2019 | BUILDING - FINAL | GWEST | Approved |