Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
06/21/2017
Applicant:
ARCHERLAND LLC
Description:
SFR
Contractors:
  • ARCHERLAND LLC

Permit Reviews

Permit Number - T17CM04833
Permit Status: Final
Permit Description: SFR
Start Date Submittal Complete Date Status  
03/08/2018 3RD PARTY REVIEW - REVISION/OTHER 03/13/2018 COMPLETED Review Details
06/21/2017 PLANS OK TO SUBMIT - RES 06/27/2017 COMPLETED Review Details
08/02/2017 3RD PARTY REVIEW - RESIDENTIAL 08/09/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM04833
Permit Status: Final
Permit Description: SFR
Total Outstanding Activity Conditions - 1
Date Name
06/21/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM04833
Permit Description: SFR
Total Completed Inspections - 27
Date Description Inspector Results Comments
08/25/2017 STEM WALL/RETAINING WALL RCAMACHO Approved
09/11/2017 REINFORCED MASONRY PRE-GROUT RCAMACHO Approved
10/27/2017 PLUMBING - SEWER HCS CONNECT NORTH Approved
10/27/2017 PLUMBING - ROUGH, SOIL NORTH Approved
11/28/2017 PLUMBING - PRE SLAB RCAMACHO Approved
11/28/2017 ELECTRIC - UFER RCAMACHO Approved
11/29/2017 ELECTRIC - UNDERGROUND RCAMACHO Approved
11/29/2017 EXCAVATION/LAYOUT REBAR & ZON RCAMACHO Approved
11/29/2017 BUILDING PRE-SLAB RCAMACHO Approved
03/21/2018 ROOF NAILING RCAMACHO Approved
04/18/2018 MECHANICAL - INTERMEDIATE RCAMACHO Approved
04/18/2018 PLUMBING - YARD WTR LINE/TEST RCAMACHO Approved
04/18/2018 PLUMBING - INTERMEDIATE RCAMACHO Approved
04/18/2018 ELECTRIC - INTERMEDIATE RCAMACHO Approved
04/18/2018 U VALUE FOR WINDOW RCAMACHO Approved
04/18/2018 STUCCO MESH RCAMACHO Approved
04/18/2018 FRAMING RCAMACHO Approved
04/18/2018 EXT METAL CLIPS/EXT SHEATHING RCAMACHO Approved
04/19/2018 TEP CLEARANCE - AM CAMACHO Approved ECO
04/19/2018 ELECTRIC - CABLE DROP RCAMACHO Approved ECO
04/30/2018 SHEET ROCK NAILING RCAMACHO Approved
08/31/2018 MECHANICAL - FINAL RCAMACHO Approved label all circuits garage sub panel
08/31/2018 PLUMBING - FINAL RCAMACHO Approved
09/04/2018 GAS CLEARANCE RCAMACHO Approved
10/17/2018 PLUMBING - GAS PRESS TEST FNL MRAMBER Approved
10/17/2018 PLUMBING - GAS PRESSURE TEST MRAMBER Approved
10/17/2018 BUILDING - FINAL MRAMBER Approved

Documents

File Name Document Type  
001_A-2.TIF CONSTRPLANS VIEW
002_A-3.TIF CONSTRPLANS VIEW
003_A-4.TIF CONSTRPLANS VIEW
004_A-5.TIF CONSTRPLANS VIEW
005_A-6.TIF CONSTRPLANS VIEW
006_A-7.TIF CONSTRPLANS VIEW
007_A-8.TIF CONSTRPLANS VIEW
008_A-9.TIF CONSTRPLANS VIEW
009_A-10.TIF CONSTRPLANS VIEW
010_A-11.TIF CONSTRPLANS VIEW
011_A-12.TIF CONSTRPLANS VIEW
012_PT1.TIF CONSTRPLANS VIEW
013_PT2.TIF CONSTRPLANS VIEW
014_PT3.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW
TRUSSES.PDF DOCUMENTS VIEW