Permit: T17CM04548
Permit Details
Apply Date:
06/12/2017
Applicant:
GUS ROUMBOS
Description:
NEW DUPLEX 2 BEDROOM/2 BATH
Architects:
- ROUMBOS, GUS DEAN
Permit Reviews
Permit Number - T17CM04548
Permit Status: Final
Permit Description: NEW DUPLEX 2 BEDROOM/2 BATH
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/16/2018 | REVISION - - 1ST | 01/16/2018 | COMPLETED |
| 06/12/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 08/11/2017 | COMPLETED |
| 08/11/2017 | RESIDENTIAL - BLDG/WWM | 09/28/2017 | COMPLETED |
| 09/28/2017 | RESUBMITTAL | 01/16/2018 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T17CM04548
Permit Description: NEW DUPLEX 2 BEDROOM/2 BATH
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/01/2017 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | FOOTPRINT OF BUILDING ONLY TO 2 WAY CLEAN OUT ONLY |
| 11/08/2017 | EXCAVATION/LAYOUT REBAR & ZON | mramber1 | Approved | |
| 11/08/2017 | BUILDING PRE-SLAB | mramber1 | Approved | |
| 11/08/2017 | ELECTRIC - UFER | mramber1 | Approved | |
| 12/06/2017 | REINFORCED MASONRY PRE-GROUT | mramber1 | Approved | |
| 01/10/2018 | PLUMBING - SEWER HCS CONNECT | mramber1 | Approved | |
| 01/10/2018 | PLUMBING - YARD WTR LINE/TEST | mramber1 | Approved | |
| 01/10/2018 | ROOF NAILING | mramber1 | Approved | |
| 01/16/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | |
| 01/16/2018 | ELECTRIC - INTERMEDIATE | DFLORES2 | Approved | |
| 01/16/2018 | FIREWALL/FIREBARRIER/FIRESTOP | DFLORES2 | Approved | |
| 01/16/2018 | FRAMING | DFLORES2 | Approved | |
| 01/16/2018 | U VALUE FOR WINDOW | mramber1 | Approved | |
| 01/16/2018 | FRAMING | mramber1 | Approved | revise plan for separation wall |
| 01/16/2018 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | fire sepatation |
| 01/16/2018 | PLUMBING - INTERMEDIATE | mramber1 | Approved | fire block |
| 01/16/2018 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
| 04/16/2018 | EXT METAL CLIPS/EXT SHEATHING | mramber1 | Approved | |
| 04/16/2018 | STUCCO MESH | mramber1 | Approved | |
| 04/16/2018 | ELECTRIC - UNDERGROUND | mramber1 | Approved | |
| 04/16/2018 | OUTDOOR LIGHTING FINAL | mramber1 | Approved | |
| 05/04/2018 | TEP CLEARANCE - AM | CAMACHO | Approved | ECO |
| 05/04/2018 | ELECTRIC - CONSTRUCTION POWER | RCAMACHO | Approved | ECO UNITS 1 & 2 |
| 05/04/2018 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | ECO UNITS 1 & 2 |
| 05/14/2018 | PLUMBING - FINAL | mramber1 | Approved | |
| 05/14/2018 | MECHANICAL - FINAL | mramber1 | Approved | |
| 05/21/2018 | BUILDING - FINAL | mramber1 | Approved | |
| 05/21/2018 | ELECTRIC - FINAL | mramber1 | Approved |