Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Apply Date:
05/12/2017
Applicant:
N/A
Description:
NEW APARTMENT
Architects:
  • ACORN, KIM BRIAN
Contractors:
  • CW BUILDERS LLC

Permit Reviews

Permit Number - T17CM03786
Permit Status: C of o
Permit Description: NEW APARTMENT
Start Date Submittal Complete Date Status  
03/08/2018 REVISION - - 1ST 04/13/2018 COMPLETED Review Details
05/02/2018 REVISION - - 2ND 05/02/2018 COMPLETED Review Details
05/02/2018 REVISION - - 2ND 05/30/2018 COMPLETED Review Details
05/12/2017 PLANS OK TO SUBMIT - COMM 05/15/2017 COMPLETED Review Details
05/15/2017 COMMERCIAL - NEW 06/23/2017 COMPLETED Review Details
06/23/2017 RESUBMITTAL 08/02/2017 COMPLETED Review Details
07/11/2018 REVISION - - 3RD 07/11/2018 COMPLETED Review Details
07/11/2018 REVISION - - 3RD 08/01/2018 COMPLETED Review Details
08/01/2018 REVISION - - 3RD 08/22/2018 COMPLETED Review Details
08/02/2017 RESUBMITTAL 08/30/2017 COMPLETED Review Details
08/30/2017 RESUBMITTAL 03/08/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM03786
Permit Status: C of o
Permit Description: NEW APARTMENT
Total Outstanding Activity Conditions - 1
Date Name
05/12/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T17CM03786
Permit Description: NEW APARTMENT
Total Completed Inspections - 41
Date Description Inspector Results Comments
05/15/2018 PLUMBING - ROUGH, SOIL TVALENC1 Approved IVRS - Inspection :*
06/01/2018 ELECTRIC - CONSTRUCTION POWER TVALENC1 Approved IVRS - Inspection :*
1- CLEAR ELECTRIC ECO TEMP POWER POLE ONLY
06/06/2018 TEP CLEARANCE - AM TVALENCIA Approved ECO
06/12/2018 ELECTRIC - UFER TVALENC1 Approved IVRS - Inspection :*
1- # 2/O CU BOND HAS BEEN LANDED ON THE HORIZONTAL STEEL REINFORCEMENT AT BOTH LOCATIONS.
06/12/2018 BUILDING PRE-SLAB TVALENC1 Approved IVRS - Inspection :*
08/29/2018 BUILDING - PROGRESS GWest Approved 100% 3rd floor trusses complete, and 100% floor deck sheathing-complete for Bldg #3.
09/18/2018 ROOF NAILING DQUINN Approved
09/25/2018 PLUMBING - YARD WTR LINE/TEST DFLORES2 Approved PLEASE CALL IN INSPECTIONS BEFORE 3 PM
10/03/2018 PLUMBING - PROGRESS DQUINN Approved DWV OK TILL TUBS ARE INSTALLED. OK FOR DROP SOFFITS TO BE INSTALLED
10/10/2018 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved OK to grout-west, north, and east up to 12 feet. South east up to 16 feet and south west up to top
10/29/2018 ELECTRIC - UNDERGROUND DQUINN Approved
10/29/2018 PLUMBING - PRE SLAB DQUINN Approved
11/02/2018 PLUMBING - INTERMEDIATE DQUINN Approved
12/03/2018 ELECTRIC - PROGRESS GWEST Approved
12/12/2018 MECHANICAL - INTERMEDIATE RCHANDLER Approved Fire caulk exhaust fan ducts.
12/12/2018 PLUMBING - ROOF DRAINS RCHANDLER Approved No test provided.
12/12/2018 ELECTRIC - INTERMEDIATE RCHANDLER Approved Fire caulk holes in common walls; check throughout.
12/19/2018 MECHANICAL - PROGRESS RCHANDLER Approved
12/19/2018 FRAMING RCHANDLER Approved
12/24/2018 EXT METAL CLIPS/EXT SHEATHING GWEST Approved
12/28/2018 SHEET ROCK NAILING B Jones Approved Building 2 3rd Floor Approved Sheet Rock Nail, incuding Shear Nail
01/04/2019 STUCCO MESH GWEST Approved
03/19/2019 ELECTRIC - SERVICE UPGRADE RCHANDLER Approved TEP ECO
03/26/2019 TEP CLEARANCE - PM RCHANDLER Approved UNITS 2206, 2103, and 2209 CODE ECO
later included 2305, was sent via email-cb, 4/1/19
04/29/2019 FIRE - FINAL MRoss Approved 1. label electrical panels
2. provide fire extinguishers prior to occupancy
3. provide FDC locking Knox plug
04/29/2019 FIRE SPKLR - FINAL MRoss Approved
04/29/2019 FIRE - ALARM FINAL MRoss Approved
05/09/2019 NPPO - FINAL DROBERTS Approved
05/09/2019 SIGN - FINAL DROBERTS Approved
05/09/2019 LANDSCAPE - FINAL DROBERTS Approved
05/09/2019 PLUMBING - ABOVE CEILING RCHANDLER Approved
05/09/2019 ELECTRIC - ABOVE CEILING RCHANDLER Approved
05/09/2019 U VALUE FOR WINDOW RCHANDLER Approved
05/09/2019 BUILDING ABOVE CEILING RCHANDLER Approved
05/09/2019 MECHANICAL - FINAL RCHANDLER Approved
05/09/2019 ELECTRIC - FINAL RCHANDLER Approved
05/10/2019 RIGHT OF WAY - FINAL MVV Approved Building #2 of the new complex has no work in right-of-way.
05/14/2019 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED
05/17/2019 MECHANICAL - ABOVE CEILING RCHANDLER Approved
07/10/2019 BUILDING - FINAL CTREVI Approved
07/10/2019 ENGINEERING - FINAL CTREVI Approved

Documents

File Name Document Type  
None CERT OF OCC VIEW
T17CM03786 C OF O.PDF CERT OF OCC VIEW
None CONSTRPLANS VIEW
None DOCUMENTS VIEW
T17CM03786 WATER REPORT.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW