Permit: T17CM03609
Permit Details
Apply Date:
05/08/2017
Applicant:
GEORGE E. HOLGUIN
Description:
DUPLEX
Architects:
- GEORGE E. HOLGUIN
Contractors:
- DURAZO CONSTRUCTION CORPORATION
Permit Reviews
Permit Number - T17CM03609
Permit Status: L of c
Permit Description: DUPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/08/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 06/08/2017 | COMPLETED |
| 06/08/2017 | RESIDENTIAL - BLDG/WWM | 07/03/2017 | COMPLETED |
| 07/10/2017 | RESUBMITTAL | 07/27/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM03609
Permit Status: L of c
Permit Description: DUPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/08/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM03609
Permit Description: DUPLEX
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
| 03/28/2018 | BUILDING PRE-SLAB | DFLORES2 | Approved | |
| 03/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | DFLORES2 | Approved | |
| 04/18/2018 | EXT METAL CLIPS/EXT SHEATHING | DFLORES2 | Approved | THIS INSPECTION WAS TO CHECK ALL CLIPS TO MOVE FORWARD, ALL H25 AND A35 CLIPS ARE IN PLACE THIS WILL GET A PARTIAL UNTIL ALL SHEATHING IS DONE |
| 04/19/2018 | FRAMING | DFLORES2 | Approved | |
| 04/19/2018 | ROOF NAILING | DFLORES2 | Approved | |
| 05/22/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 05/22/2018 | STUCCO MESH | ESTEVEN1 | Approved | APPROVED |
| 05/30/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | |
| 05/30/2018 | ELECTRIC - UFER | DFLORES2 | Approved | |
| 06/04/2018 | ELECTRIC - INTERMEDIATE | DFLORES2 | Approved | |
| 06/04/2018 | FIREWALL/FIREBARRIER/FIRESTOP | DFLORES2 | Approved | |
| 06/06/2018 | SHEET ROCK NAILING | DFLORES2 | Approved | |
| 07/26/2018 | ELECTRIC - CONSTRUCTION POWER | DFLORES2 | Approved | CLEAR ECO |
| 07/26/2018 | ELECTRIC - CABLE DROP | DFLORES2 | Approved | |
| 07/27/2018 | TEP CLEARANCE - AM | DFLORES | Approved | ECO |
| 09/28/2018 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | Please approve those as well in order to close out. |
| 09/28/2018 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | Please approve those as well in order to close out. |
| 09/28/2018 | U VALUE FOR WINDOW | MHASSAN | Approved | Please approve those as well in order to close out. |
| 09/28/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | Please close out this permit. |
| 09/28/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | Please close out this permit. |
| 09/28/2018 | MECHANICAL - FINAL | MHASSAN | Approved | Please close out this permit. |
| 09/28/2018 | PLUMBING - FINAL | MHASSAN | Approved | Please close out this permit. |
| 09/28/2018 | ELECTRIC - FINAL | MHASSAN | Approved | |
| 09/28/2018 | BUILDING - FINAL | MHASSAN | Approved |